USA › Arizona › Maricopa County

Maricopa County

23 data center projects we know about. 25 cities, towns and unincorporated areas.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

Projects

Approved, not built yet

Project Eagle (formerly Project Baccara) data center campus and gas power plant near Luke Air Force Base

Unincorporated Maricopa County, Maricopa County

160 acres

🕒 Sept 24, 2026: Glendale Planning Commission voted 4-2 to recommend rezoning the site after annexation.

Approved, not built yet

Hassayampa Ranch data center campus west of the White Tank Mountains

Unincorporated Maricopa County, Maricopa County

2,000 acres

🕒 April 8, 2026: Maricopa County supervisors approved the Hassayampa Ranch data center project.

Approved, not built yet

Tonopah mixed-use campus with data centers and a movie studio

Unincorporated Maricopa County, Maricopa County

900 acres

🕒 Sept 5, 2026: Developer announced a $6-10 billion plan with a data center campus, movie studio, amusem…

Reported in the news, not confirmed yet

Stopped or cancelled

Project Range data center campus near Yuma Road (withdrawn)

Unincorporated Maricopa County, Maricopa County

1,000 acres

🕒 April 2024: Tract withdrew the request after pushback from Goodyear and Buckeye staff and residents.

Approved, not built yet

Buckeye Tech Corridor data center park

Buckeye, Maricopa County

2,000 acres

🕒 Aug 6, 2024: Buckeye City Council unanimously approved a plan change and a development agreement with…

Stopped or cancelled

Price Road Innovation Campus (rejected)

Chandler, Maricopa County

40 acres

🕒 Dec 11, 2025: Chandler City Council voted unanimously to reject the rezoning after hours of public com…

Stopped or cancelled

Laveen data center campus by Vintage Partners (dropped)

Phoenix, Maricopa County

63 acres

🕒 March 2026: Developer said it scrapped the data center and will plan shops, restaurants and up to 1,…

Approved, not built yet

Menlo Digital data center campus at Thistle Landing, Ahwatukee

Phoenix, Maricopa County

38 acres

🕒 July 2026: Phoenix City Council approved removing drainage and water line easements on the site.

Reported in the news, not confirmed yet

Approved, not built yet

EdgeCore data center campus in Eastmark, Mesa

Mesa, Maricopa County

90 acres

🕒 March 11, 2026: Mesa Planning and Zoning Board approved cutting the project from 2.1 million to 1.2 mill…

Reported in the news, not confirmed yet

Approved, not built yet

NTT data center campus at Pecos and Crismon roads, Mesa

Mesa, Maricopa County

170 acres

🕒 June 2026: Mesa Planning and Zoning Board voted 4-0 to recommend approval; the Council vote was pus…

Reported in the news, not confirmed yet

Approved, not built yet

CyrusOne data center campus on Elliot Road, Mesa

Mesa, Maricopa County

68 acres

🕒 July 24, 2024: Mesa Planning and Zoning Board approved the site plan 4-3 after neighbors raised concern…

Reported in the news, not confirmed yet

Approved, not built yet

Merit Legacy Technology Park, Mesa

Mesa, Maricopa County

43 acres

🕒 Aug 26, 2024: Mesa City Council unanimously approved the plan amendment, annexation, zoning and develo…

Being built

Prime Data Centers Phoenix campus (PHX01) in Avondale

Avondale, Maricopa County

66.5 acres

🕒 May 21, 2026: Prime broke ground on the first three of five 48-megawatt buildings.

Reported in the news, not confirmed yet

Approved, not built yet

Compass Datacenters PHX II campus, El Mirage

El Mirage, Maricopa County

120 acres

🕒 June 2024: Compass bought the 120 acres for $79.3 million.

Being built

Microsoft data center campus at Dysart Road and Northern Parkway, El Mirage

El Mirage, Maricopa County

433 acres · for Microsoft

🕒 May 31, 2024: Microsoft paid $258 million for about 283 acres next to its existing 150-acre site.

Built & running

Microsoft data center campus south of Phoenix Goodyear Airport

Goodyear, Maricopa County

300 acres · for Microsoft

🕒 March 6, 2023: Goodyear approved a deal: Microsoft pays $36 million toward a wastewater plant expansion…

Built & running

Google data center campus at Elliot and Sossaman roads, Mesa

Mesa, Maricopa County

187 acres · for Google

🕒 2024: Plans for the second building (Redhawk Phase 2) went to Mesa for review.

Approved, not built yet

Data center and solar campus at 491st Avenue and Thomas Road, Tonopah

Unincorporated Maricopa County, Maricopa County

638 acres

🕒 Feb 2026: Maricopa County supervisors approved a plan change and rezoning to light industrial (IND…

Proposed

Belmont Energy Center: solar, gas and data center site near Tonopah

Unincorporated Maricopa County, Maricopa County

3,100 acres

🕒 2026: Copia Power filed to rezone about 3,100 acres for solar, a gas plant, batteries and data…

Reported in the news, not confirmed yet

Status unclear

Aligned Data Centers office park conversion in Deer Valley, Phoenix

Phoenix, Maricopa County

🕒 March 2026: Aligned was among at least 11 landowners that filed Prop 207 claims against Phoenix's ne…

Reported in the news, not confirmed yet

Approved, not built yet

QTS data center campus at Hermosa Ranch, Avondale

Avondale, Maricopa County

206 acres

🕒 July 2024: QTS bought 206 acres for $246.8 million.

Being built

QTS Phoenix 3 data center campus on Camelback Road

Glendale, Maricopa County

375 acres

🕒 July 2024: QTS said a third Phoenix-area campus in Glendale was in design.

Reported in the news, not confirmed yet

Built & running

Meta data center campus in Mesa

Mesa, Maricopa County

for Meta

🕒 Jan 30, 2025: Meta held the grand opening of the first phase.

Local votes and rules

📜 Data center rules · Gilbert

The planning commission voted Aug. 5, 2026 to recommend strict data center rules: industrial zones only, at least 650 feet from homes, no town drinking water for cooling and no open evaporative cooling. Town council vote was expected in September. Gilbert has no data center applications.

Aug 5, 2026Source

📜 Data center rules · Goodyear

City council unanimously passed a full rewrite of its zoning code, the first since 1999. Data centers are allowed in industrial zones with conditions, and must stay 300 feet from homes, with new noise standards.

July 6, 2026Source

✅ Approved · Maricopa County

County supervisors voted 4-1 to give Project Baccara a special permit needed near Luke Air Force Base. The 160-acre site off Olive Avenue and Litchfield Road would hold two data centers and a gas power plant, about 400 feet from a dozen homes. It still needs an air permit.

May 6, 2026Source

✅ Approved · Mesa

City planning board approved a smaller EdgeCore data center in Eastmark: two buildings (1.2 million square feet, down from 2.1 million). Generator tests only 9 a.m. to 9 p.m. It still needs a city council vote.

March 11, 2026Source

🗺️ Zoning change · Buckeye

City council passed Ordinance 04-26, lifting old limits that kept a 157-acre site to hydrogen production. The land is now open to heavy industry; the owner is interested in a data center, which would still need a conditional use permit.

March 3, 2026Source

📌 Other · Phoenix

At least 11 landowners have filed Prop 207 claims saying the 2025 data center rules lowered their land value. Instead of paying, the city has given waivers in some cases that let projects go ahead, such as a planned Aligned Data Centers campus in Deer Valley.

March 2026Source

✋ Turned down · Chandler

City council voted unanimously to reject a rezoning for an AI data center on 40 acres in the Price Road corridor, asked for by Active Infrastructure. More than 250 people wrote against it.

Dec 11, 2025Source

📜 Data center rules · Maricopa County

County supervisors updated zoning for data centers on unincorporated land. They are allowed only in the IND-2 and IND-3 industrial zones; other land must be rezoned first.

Dec 10, 2025Source

🗺️ Zoning change · Maricopa County

County supervisors unanimously rezoned about 2,000 acres west of the White Tank Mountains for industrial use. This clears the way for Hassayampa Ranch, a planned data center campus over 1 gigawatt led by Arizona Land Consulting.

Dec 10, 2025Source

📜 Data center rules · Mesa

City council unanimously passed data center zoning rules, in effect Aug. 8, 2025. Data centers need council approval, may only go in industrial zones, must be 400 feet from homes and no taller than 60 feet, and must do an early review of power and water use.

July 8, 2025Source

📜 Data center rules · Phoenix

City council unanimously changed the general plan and zoning code for data centers. They may only go in industrial and some commercial areas, and need a special permit. They must reduce noise if within 300 feet of homes and stay half a mile from high-capacity transit.

July 2, 2025Source

📜 Data center rules · Chandler

City council unanimously passed data center rules, in effect Jan. 5, 2023. Data centers need a special rezoning (PAD). Builders must do a noise study before building and keep noise at that baseline, check noise for five years, hold neighborhood meetings and tell residents about generator tests.

Dec 5, 2022Source