Aligned Data Centers office park conversion in Deer Valley, Phoenix
Also called: Aligned PHX-08, Aligned PHX-09
Aligned Data Centers wants to turn a vacant office park in north Phoenix into a data center campus. Phoenix's 2025 rules made it harder to build data centers near homes, so Aligned filed a claim for lost value. The city and Aligned were negotiating in 2026.
Where things stand: Aligned filed a Prop 207 claim after Phoenix's 2025 data center rules; in March 2026 its lawyer said they were working on a deal with the city.
๐ Latest update (March 2026): Aligned was among at least 11 landowners that filed Prop 207 claims against Phoenix's new data center rules; talks with the city were ongoing.
What we know
- ๐ WhereFormer office buildings at 3151 and 3202 W. Behrend Drive in Deer Valley, near Interstate 17 and Loop 101., Phoenix, Maricopa County
- ๐ข CompanyAligned Data Centers
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did Phoenix and Aligned reach a Prop 207 waiver deal for the Deer Valley site? ๐ I'll find out
- How much power would the converted buildings use? ๐ I'll find out
- How many diesel backup generators would be on site? ๐ I'll find out
What happened so far
- Sept 2022Aligned bought two Deer Valley office buildings for $93 million to turn into data centers.
- March 2026Aligned was among at least 11 landowners that filed Prop 207 claims against Phoenix's new data center rules; talks with the city were ongoing.
Local votes and rules
๐ Other
At least 11 landowners have filed Prop 207 claims saying the 2025 data center rules lowered their land value. Instead of paying, the city has given waivers in some cases that let projects go ahead, such as a planned Aligned Data Centers campus in Deer Valley.
๐ Data center rules
City council unanimously changed the general plan and zoning code for data centers. They may only go in industrial and some commercial areas, and need a special permit. They must reduce noise if within 300 feet of homes and stay half a mile from high-capacity transit.
An aerial photo of the area.
Where this comes from
- Phoenix negotiates with developers after data center zoning rules trigger claims ยท ABC15 ยท March 2026
- Phoenix faces growing legal pressure over new data center rules ยท AZFamily ยท March 26, 2026
- Aligned: PHX-08 ยท Baxtel ยท 2026
- Geocoded address: 3151 W Behrend Dr, Phoenix ยท Esri World Geocoder ยท Oct 7, 2026
See something wrong? Tell us and we'll fix it.