Send us a tip
Approved, not built yet

Merit Legacy Technology Park, Mesa

Also called: Merit Legacy Technology Park

Merit Partners plans a data center park with three data halls on about 43 acres in southeast Mesa. The City Council approved it in 2024, the same night it approved the larger campus next door.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Mesa City.

Where things stand: Approved, not built yet Mesa City Council unanimously approved it on Aug 26, 2024.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 26, 2024): Mesa City Council unanimously approved the plan amendment, annexation, zoning and development agreement.

What we know

  • 📍 WhereAbout 43 acres at the northwest corner of Crismon and Pecos roads in southeast Mesa, across Crismon Road from the Pacific Proving campus. Map point is inside that corner., Mesa, Maricopa County
  • 🏢 CompanyMerit Partners
  • 🌳 Size43 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the Merit Legacy site, and has construction started? 🙋 I'll find out ·
  • How much power and water will it use? 🙋 I'll find out ·
  • Which company will use it? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 26, 2024
      Mesa City Council unanimously approved the plan amendment, annexation, zoning and development agreement.

    Local votes and rules

    ✅ Approved

    City planning board approved a smaller EdgeCore data center in Eastmark: two buildings (1.2 million square feet, down from 2.1 million). Generator tests only 9 a.m. to 9 p.m. It still needs a city council vote.

    March 11, 2026

    📜 Data center rules

    City council unanimously passed data center zoning rules, in effect Aug. 8, 2025. Data centers need council approval, may only go in industrial zones, must be 400 feet from homes and no taller than 60 feet, and must do an early review of power and water use.

    July 8, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Major data center projects by Pacific Proving and Merit Partners receive approval · ABC15 · Aug 30, 2024
    2. Mesa City Council approves two data center projects · DatacenterDynamics · Aug 2024
    3. Merit Legacy Technology Park (NWC Crismon and Pecos roads) · AZBEX · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.