Approved, not built yetBig (AI-size): 2,000 acres

Buckeye Tech Corridor data center park

Also called: Buckeye Tech Corridor

Tract plans a giant data center park on nearly 2,000 acres in Buckeye, with dozens of buildings built over about 15 years. The city approved it in 2024 and agreed to repay up to $50 million of road and pipe costs later. Tract says it could bring 500 permanent jobs.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Buckeye City.

Where things stand: Approved, not built yet Buckeye City Council approved the plan and a development deal in Aug 2024. Build-out could take 15 years.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 6, 2024): Buckeye City Council unanimously approved a plan change and a development agreement with Tract.

What we know

  • 📍 WhereAbout 2,100 acres generally bounded by Yuma Road on the north, Southern Avenue on the south, Johnson Road on the east and 323rd Avenue on the west. Map point is the middle of that area., Buckeye, Maricopa County
  • 🏢 CompanyTract
  • 🌳 Size2,000 acres
  • 💵 Cost$20 billion
  • 💸 Tax breaksThe city will pay the developer back up to $50 million for roads and pipes, but only after the project brings the city $60 million in revenue.
  • 👷 Jobs promised500

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which companies will build data centers in the park? 🙋 I'll find out ·
  • Where will the power come from, and will new power lines be built? 🙋 I'll find out ·
  • Where will the water come from and how much will be used? 🙋 I'll find out ·
  • Has any building permit been issued yet? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 6, 2024
      Buckeye City Council unanimously approved a plan change and a development agreement with Tract.

    Local votes and rules

    🗺️ Zoning change

    City council passed Ordinance 04-26, lifting old limits that kept a 157-acre site to hydrogen production. The land is now open to heavy industry; the owner is interested in a data center, which would still need a conditional use permit.

    March 3, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. $20 billion data center campus gets green light in Buckeye · KTAR News · Aug 12, 2024
    2. Buckeye council advances $20B investment · West Valley View · Aug 2024
    3. Buckeye Tech Corridor · Data Center Map · 2026
    4. Buckeye Planning Commission recommends Buckeye Tech Corridor master plan · AZBEX · Oct 8, 2026