Approved, not built yet

NTT data center campus at Pecos and Crismon roads, Mesa

NTT wants to build seven data center buildings, about 2.3 million square feet, on 170 acres of the former GM proving grounds in southeast Mesa. Mesa first approved data centers here in 2024. NTT says its cooling is a sealed loop that does not evaporate water. Neighbors worry about water use, size and home values.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: The site was rezoned for data centers in Aug 2024. NTT's changed plan won a 4-0 planning board vote in June 2026; the City Council vote on the changes was postponed.

🕒 Latest update (June 2026): Mesa Planning and Zoning Board voted 4-0 to recommend approval; the Council vote was pushed to later in summer.

What we know

  • 📍 Where10126 E. Pecos Rd., the northeast corner of Pecos and Crismon roads in southeast Mesa (former GM proving grounds), about a mile north of Queen Creek., Mesa, Maricopa County
  • 🏢 CompanyNTT Global Data Centers
  • 🌳 Size170 acres
  • ❄️ Coolingclosed-loop water cooling filled once, with no evaporative cooling (developer's plan)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Nov 2023
    Pacific Proving asked Mesa to allow a 360-megawatt data center campus on the former GM proving grounds.
  • Aug 26, 2024
    Mesa City Council unanimously approved annexation, rezoning and a development agreement for the Pacific Proving Technology Campus.
  • March 2025
    NTT Data Group bought the 173-acre site for $300 million.
  • June 2026
    Mesa Planning and Zoning Board voted 4-0 to recommend approval; the Council vote was pushed to later in summer.

Local votes and rules

✅ Approved

City planning board approved a smaller EdgeCore data center in Eastmark: two buildings (1.2 million square feet, down from 2.1 million). Generator tests only 9 a.m. to 9 p.m. It still needs a city council vote.

March 11, 2026

📜 Data center rules

City council unanimously passed data center zoning rules, in effect Aug. 8, 2025. Data centers need council approval, may only go in industrial zones, must be 400 feet from homes and no taller than 60 feet, and must do an early review of power and water use.

July 8, 2025
🛰️ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Big data center near Queen Creek passes first review · Queen Creek Tribune · June 7, 2026
  2. Major data center projects by Pacific Proving and Merit Partners receive approval · ABC15 · Aug 30, 2024
  3. NTT Data Group buys land in Mesa · KTAR News · March 2025
  4. Developer Proposes 1.4M SF Data Center Campus On Former GM Testing Site In Arizona · Bisnow · Nov 6, 2023
  5. Mesa considers new data center project off SR 24 · ABC15 · 2026
  6. Geocoded address: 10126 E Pecos Rd, Mesa · Esri World Geocoder · Oct 7, 2026