Prime Data Centers Phoenix campus (PHX01) in Avondale

Also called: Prime PHX01

Prime Data Centers is building five large data center buildings in Avondale, using up to 240 megawatts in all. Construction of the first three started in May 2026. The project is worth about $3 billion.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Construction of the first three buildings started in May 2026.

๐Ÿ•’ Latest update (May 21, 2026): Prime broke ground on the first three of five 48-megawatt buildings.

What we know

  • ๐Ÿ“ Where3700 S. Avondale Blvd., south of Avondale Boulevard and Lower Buckeye Road., Avondale, Maricopa County
  • ๐Ÿข CompanyPrime Data Centers
  • ๐ŸŒณ Size66.5 acres
  • โšก Power it needs240 megawatts (about as much as 192,000 homes)
  • ๐Ÿ’ต Cost$3 billion

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 21, 2026
    Prime broke ground on the first three of five 48-megawatt buildings.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Prime Data Centers breaks ground on three buildings at its 240MW campus in Phoenix ยท IREI ยท May 22, 2026
  2. Geocoded address: 3700 S Avondale Blvd ยท Esri World Geocoder ยท Oct 7, 2026

See something wrong? Tell us and we'll fix it.