Approved, not built yetBig (AI-size): 108 megawatts

Compass Datacenters PHX II campus, El Mirage

Also called: Compass PHX II

Compass plans three one-story data center buildings in El Mirage, using about 108 megawatts in all. The city approved the site plan in 2023 and Compass bought the land in 2024.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of El Mirage City.

Where things stand: Approved, not built yet City approved the site plan in late 2023; Compass bought the land in 2024. Trackers list the first building for 2026.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (June 2024): Compass bought the 120 acres for $79.3 million.

What we know

  • 📍 WhereAbout 120 acres at El Mirage Road and Peoria Avenue (southwest corner), in the Copperwing industrial area. Map point is that corner., El Mirage, Maricopa County
  • 🏢 CompanyCompass Datacenters
  • 🌳 Size120 acres
  • ⚡ Power it needs108 megawatts (about as much as 86,400 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the first Compass building in El Mirage under construction or running? 🙋 I'll find out ·
  • How will it be cooled and how much water will it use? 🙋 I'll find out ·
  • Which company will use it? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2023
      El Mirage approved the site plan.
    • Feb 2023
      Compass filed plans with El Mirage for three 36-megawatt buildings.
    • June 2024
      Compass bought the 120 acres for $79.3 million.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. New Data Center Proposed in El Mirage · AZBEX · Feb 17, 2023
    2. Compass Datacenters Buys 120 Acres Near Phoenix For New Campus · Bisnow · June 10, 2024
    3. Geocoded road corner: El Mirage Rd and Peoria Ave · Esri World Geocoder · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.