QTS Phoenix 3 data center campus on Camelback Road
Also called: QTS PHX 3
QTS plans a very large campus of up to 16 data center buildings on about 375 acres in west Glendale, near Loop 303. At full size it could use 750 megawatts. QTS already lists several buildings there.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Glendale City.
Where things stand: Being built QTS bought the land in 2022 and filed plans in 2023. QTS lists several buildings with Camelback Road addresses.
❓ 3 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (July 2024): QTS said a third Phoenix-area campus in Glendale was in design.
What we know
- 📍 WhereAbout 375 acres north of Camelback Road and west of Loop 303 along Cotton Lane (buildings at 17236-17428 W. Camelback Rd.)., Glendale, Maricopa County
- 🏢 CompanyQTS Data Centers
- 🏛️ Owned byBlackstone
- 🌳 Size375 acres
- ⚡ Power it needs750 megawatts (about as much as 600,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many QTS Phoenix 3 buildings are running or being built now? 🙋 I'll find out ·
- How will the campus be cooled and how much water will it use? 🙋 I'll find out ·
- How many diesel backup generators will be on site? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the 2025 Sentinel-2 satellite picture of the map point: cleared land, construction and finished data center halls stand at the point.
What happened so far
- July 2022QTS bought the site for $255.3 million.
- 2023QTS filed plans with Glendale for 16 buildings, about 3 million sq ft.
- July 2024QTS said a third Phoenix-area campus in Glendale was in design.
Local votes and rules
✅ Approved
Glendale City Council approved bringing about 160 acres near Litchfield Road and Olive Avenue into the city and rezoning them for Project Eagle: three data center buildings, a gas power plant with 18 turbines and an APS substation. The developer must meet Luke Air Force Base standards. The planning commission had recommended it 4-2.
Drag the slider to compare the land before and now.
Where this comes from
- QTS files for 750MW campus in Phoenix, Arizona · DatacenterDynamics · 2023
- Phoenix 3 Data Center Campus · QTS Data Centers · 2026
- QTS buys Avondale land for data center · AZBEX · July 26, 2024
- Geocoded address: 17408 W Camelback Rd · Esri World Geocoder · Oct 7, 2026
- Sentinel-2 cloudless 2025 satellite mosaic (EOX) · EOX IT Services (contains Copernicus Sentinel data) · Oct 8, 2026
See something wrong? Tell us and we'll fix it.