Microsoft data center campus at Dysart Road and Northern Parkway, El Mirage
Also called: Microsoft El Mirage
Microsoft is growing a data center campus in El Mirage's Copperwing industrial area. It already had 150 acres and bought 283 more acres in 2024 for $258 million. The city has approved several more buildings.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of El Mirage City.
Where things stand: Being built Microsoft has one campus here and bought 283 more acres in May 2024. More buildings were in permitting in 2024.
❓ 3 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (May 31, 2024): Microsoft paid $258 million for about 283 acres next to its existing 150-acre site.
What we know
- 📍 WhereEast of Dysart Road and north of Northern Parkway in the Copperwing industrial area, where Microsoft's data center buildings stand., El Mirage, Maricopa County
- 🏢 CompanyMicrosoft
- 👤 Built forMicrosoft
- 🌳 Size433 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many buildings are running and how many are being built? 🙋 I'll find out ·
- How much power and water does the campus use? 🙋 I'll find out ·
- How many diesel backup generators are on site? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the 2025 Sentinel-2 satellite picture of the map point: large data center halls and a substation stand at the point.
What happened so far
- April 2024El Mirage City Council approved a site plan change for a third 245,000 sq ft data center building.
- May 2024El Mirage approved a development agreement for three more data center buildings (750,000 sq ft) on land Microsoft then bought.
- May 31, 2024Microsoft paid $258 million for about 283 acres next to its existing 150-acre site.
Drag the slider to compare the land before and now.
Where this comes from
- Microsoft acquires nearly 300 acres for data center growth in El Mirage · ABC15 · June 2024
- Microsoft buys land in El Mirage for data center · Arizona Technology Council · June 2024
- Geocoded road corner: Dysart Rd and Northern Pkwy · Esri World Geocoder · Oct 7, 2026
- Microsoft Data Center, El Mirage · OpenStreetMap contributors (ODbL) · Oct 8, 2026
- Sentinel-2 cloudless 2025 satellite mosaic (EOX) · EOX IT Services (contains Copernicus Sentinel data) · Oct 8, 2026
See something wrong? Tell us and we'll fix it.