Project Eagle (formerly Project Baccara) data center campus and gas power plant near Luke Air Force Base
Also called: Project Baccara, Project Eagle, Baccara Power
Takanock plans three large data center buildings, 18 gas turbines (about 700 megawatts) and an APS substation on 160 acres near Litchfield Road and Olive Avenue, north of Luke Air Force Base. Glendale City Council approved bringing the land into the city and rezoning it on Oct. 27, 2026. Many neighbors in Surprise and Glendale oppose it over air pollution, noise and groundwater.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Maricopa County Board of Supervisors (for land outside city and town limits).
Where things stand: Approved, not built yet Glendale City Council approved annexing and rezoning the 160-acre site on Oct. 27, 2026. The city says construction should start in November 2026. An air permit is still needed.
- Oct 27, 2026: Glendale, Maricopa County: project approved Source
❓ 4 open questions about it: see below.
Last checked Nov 3, 2026.
🕒 Latest update (Oct 27, 2026): Glendale City Council approved annexing the 160-acre site into Glendale and rezoning it for three data center buildings, a gas power plant with 18 turbines and an APS substation. The city ordinance requires the developer to meet Luke Air Force Base standards.
What we know
- 📍 Where160 acres north of Olive Avenue, about half a mile west of Litchfield Road, on a county island north of Luke Air Force Base. Map point is placed from that description., Unincorporated Maricopa County, Maricopa County
- 🏢 CompanyTakanock (with Montera Infrastructure)
- 🌳 Size160 acres
- ⚡ Power it needs700 megawatts (about as much as 560,000 homes)
- 🔌 Where the power comes fromIts own natural gas power plant on site: 18 gas turbines, about 700 megawatts (Baccara Power). The developer supplies its own power, so APS and local irrigation district customers are not supposed to pay for it.
- 💵 Cost$36 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the air permit for the gas power plant been granted? 🙋 I'll find out ·
- Which company will use the data centers? 🙋 I'll find out ·
- How much groundwater will the site use each day? 🙋 I'll find out ·
- How many diesel backup generators will the site have? 🙋 I'll find out ·
What happened so far
- Feb 4, 2026Arizona Corporation Commission voted 5-0 to approve the site permit for the 700-megawatt gas plant.
- April 2026Glendale City Council unanimously approved a pre-annexation development agreement.
- May 6, 2026Maricopa County supervisors approved the military compatibility permit 4-1 despite opposition.
- Aug 25, 2026Glendale City Council held a workshop on annexing the site; the project is now called Project Eagle, with three data center buildings.
- Sept 22, 2026Glendale City Council held a public hearing on annexation; no vote yet.
- Sept 24, 2026Glendale Planning Commission voted 4-2 to recommend rezoning the site after annexation.
- Oct 27, 2026Glendale City Council approved annexing the 160-acre site into Glendale and rezoning it for three data center buildings, a gas power plant with 18 turbines and an APS substation. The city ordinance requires the developer to meet Luke Air Force Base standards.
Local votes and rules
✅ Approved
Glendale City Council approved bringing about 160 acres near Litchfield Road and Olive Avenue into the city and rezoning them for Project Eagle: three data center buildings, a gas power plant with 18 turbines and an APS substation. The developer must meet Luke Air Force Base standards. The planning commission had recommended it 4-2.
Drag the slider to compare the land before and now.
Where this comes from
- Vice Chair Walden Releases Statement on Project Baccara · Arizona Corporation Commission · Feb 6, 2026
- Massive data center approved near Luke Air Force Base despite opposition · AZFamily · May 7, 2026
- Arizona Corporation Commission Approves New Baccara Gas Plant in Residential Area · Sierra Club · Feb 2026
- 160-acre Project Baccara is recommended for approval in Maricopa County, Arizona · DatacenterDynamics · 2026
- New data center planned for Glendale sparks concerns among residents · FOX 10 Phoenix · April 28, 2026
- Arizona AG calls for statewide pause on new data centers, a Glendale project could be in the crosshairs · ABC15 · Aug 2026
- Controversial West Valley data center moves toward Glendale annexation vote · ABC15 · Sept 2026
- Geocoded road corner: W Olive Ave and N Litchfield Rd (site is half a mile west) · Esri World Geocoder · Oct 7, 2026
- Maricopa County Data Center Project Moves Toward Approval Despite Pushback · Bisnow · Sept 28, 2026
- Phoenix CRE Brief · The Land Letter · Sept 24, 2026
- Glendale approves Project Eagle data center development · KJZZ · Oct 28, 2026
- Glendale City Council approves Project Eagle data center, natural gas power facility · ABC15 · Oct 28, 2026
- Glendale approves major step to start construction on data center · AZFamily · Oct 29, 2026