No project in Queen Creek Town, but 7 nearby

Who decides here: the Town Council of Queen Creek Town votes on zoning. The Maricopa County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Nearby (within 15 miles)

Approved, not built yetabout 4 miles away

NTT data center campus at Pecos and Crismon roads, Mesa

Mesa, Maricopa County

170 acres

🕒 June 2026: Mesa Planning and Zoning Board voted 4-0 to recommend approval; the Council vote was pus…

Reported in the news, not confirmed yet

Approved, not built yetabout 4 miles away

Merit Legacy Technology Park, Mesa

Mesa, Maricopa County

43 acres

🕒 Aug 26, 2024: Mesa City Council unanimously approved the plan amendment, annexation, zoning and develo…

Built & runningabout 7 miles away

Meta data center campus in Mesa

Mesa, Maricopa County

396 acres · for Meta

🕒 Jan 30, 2025: Meta held the grand opening of the first phase.

Approved, not built yetabout 8 miles away

EdgeCore data center campus in Eastmark, Mesa

Mesa, Maricopa County

90 acres

🕒 March 11, 2026: Mesa Planning and Zoning Board approved cutting the project from 2.1 million to 1.2 mill…

Reported in the news, not confirmed yet

Approved, not built yetabout 8 miles away

CyrusOne data center campus on Elliot Road, Mesa

Mesa, Maricopa County

68 acres

🕒 July 24, 2024: Mesa Planning and Zoning Board approved the site plan 4-3 after neighbors raised concern…

Reported in the news, not confirmed yet

Built & runningabout 8 miles away

Google data center campus at Elliot and Sossaman roads, Mesa

Mesa, Maricopa County

187 acres · for Google

🕒 2024: Plans for the second building (Redhawk Phase 2) went to Mesa for review.

Approved, not built yetabout 12 miles away

Dobson Farms data centers and Florence Tech Park

Florence, Pinal County

1,619 acres

🕒 Oct 2, 2025: Florence Planning and Zoning Commission heard the rezoning requests.

Reported in the news, not confirmed yet

Local votes and rules

✅ Approved · Maricopa County

County supervisors voted 4-1 to give Project Baccara a special permit needed near Luke Air Force Base. The 160-acre site off Olive Avenue and Litchfield Road would hold two data centers and a gas power plant, about 400 feet from a dozen homes. It still needs an air permit.

May 6, 2026Source

📜 Data center rules · Maricopa County

County supervisors updated zoning for data centers on unincorporated land. They are allowed only in the IND-2 and IND-3 industrial zones; other land must be rezoned first.

Dec 10, 2025Source

🗺️ Zoning change · Maricopa County

County supervisors unanimously rezoned about 2,000 acres west of the White Tank Mountains for industrial use. This clears the way for Hassayampa Ranch, a planned data center campus over 1 gigawatt led by Arizona Land Consulting.

Dec 10, 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Queen Creek Town.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Queen Creek Town. Nothing else.

⚡ Your electric company

Depending on where you live in Queen Creek Town: Tohono O'odham Utility Authority (not available) or Gila River Indian Utility Authority (gricua) (co-op (owned by its members)) or Ocotillo Water Conserv. Dist. (not available) or Maricopa County M W C Dist #1 (not available) or Harquahala Valley Pwr District (not available) or Usbia-san Carlos Project (public) or Tonopah Irrigation District (not available) or Buckeye Water C&d District (not available) or Salt River Project (public) or Wapa-- Western Area Power Administration (public) or Electrical Dist No8 Maricopa (public) or City of Mesa (run by the town).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Arizona.