πŸ“£ Report Something
USA β€Ί Arizona β€Ί Pinal County β€Ί Florence Town
Approved, not built yet

Dobson Farms data centers and Florence Tech Park

Also called: Florence Tech Park, Able Tech Park Data Center, Dobson Farms EdgeCore Data Center, Dobson Farms East, Dobson Farms West

Ryan Companies and EdgeCore plan data center and industrial campuses on about 1,600 acres of farmland in Florence. Plans show up to 10 two-story data center buildings and several substations. The town approved the rezoning in October 2025.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Town of Florence approved rezoning for 1,619 acres of data center and industrial land in October 2025. No building permits reported yet.

πŸ•’ Latest update (Oct 2, 2025): Florence Planning and Zoning Commission heard the rezoning requests.

What we know

  • πŸ“ WhereFarmland around Arizona Farms Road and Attaway Road in the Dobson Farms area of Florence, Florence, Pinal County
  • 🏒 CompanyRyan Companies and EdgeCore Digital Infrastructure
  • 🌳 Size1,619 acres
  • πŸ”Œ Where the power comes fromSalt River Project (SRP) substations; plans show new substations on site
  • ❄️ Coolingelectric cooling, not water, according to the applicant at a planning hearing
  • πŸ‘· Jobs promised800

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 2025
    Developers asked Florence to change its general plan for three pieces of Dobson Farms (780, 600 and 239 acres) to allow data centers and industry.
  • Oct 2025
    Town of Florence approved rezoning for about 1,619 acres for data centers and industry.
  • Oct 2, 2025
    Florence Planning and Zoning Commission heard the rezoning requests.

Local votes and rules

πŸ—ΊοΈ Zoning change

The Town of Florence approved rezoning about 1,619 acres of Dobson Farms for data centers and industry, for Ryan Companies and EdgeCore.

Oct 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Major general plan amendments requested for 1,800-acre Florence area Β· AZBEX Β· Sept 5, 2025
  2. Pinal County data center projects update Β· Rose Law Group Reporter Β· April 2026
  3. Florence Tech Park (Ryan Companies, Dobson Farms) Β· More Than Just Parks Data Center Tracker Β· Oct 7, 2025
  4. Ryan Companies and EdgeCore target data center developments outside Phoenix, Arizona Β· DatacenterDynamics Β· Oct 2025

See something wrong? Tell us and we'll fix it.