Amazon Bridgefield Tech Center (former GW Virginia campus, Ashburn)
Loudoun County, Loudoun County
122 acres Β· for Amazon Web Services
π July 28, 2026: Amazon filed a first plan for four data center buildings (805,092 square feet).
ProposedB.F. Saul data centers on Shaw Road (Sterling)
Loudoun County, Loudoun County
37.24 acres
π Sept 2026: Loudoun Planning Commission voted against the rezoning.
ProposedCochran Tech data center (Cochran Mill Road, near Leesburg)
Loudoun County, Loudoun County
π May 5, 2026: Board voted 6-1-1 to reconsider and send the plan back to the Planning Commission.
ProposedPrologis Concorde Industrial Park data center conversion (Sterling)
Loudoun County, Loudoun County
17 acres
π Feb 11, 2026: Board of Supervisors held its review of the rezoning.
Approved, not built yetCross Mill Center data center (near Leesburg Executive Airport)
Loudoun County, Loudoun County
22 acres
π July 15, 2025: Board of Supervisors approved the rezoning 5-4.
Approved, not built yetGreenlin Park data center campus (Dulles Greenway, south of Leesburg)
Loudoun County, Loudoun County
83 acres
π Feb 19, 2025: Board of Supervisors approved the rezoning.
ProposedLeesburg Gateway data center plan (Peterson Companies)
Leesburg, Loudoun County
107 acres
π Jan 26, 2026: Town Council cancelled its public hearing at the developer's request.
ProposedQuantum Park data centers (Ashburn)
Loudoun County, Loudoun County
40 acres
π April 15, 2026: Supervisors moved the plan to a May 19 vote; several said they would vote no.
Approved, not built yetBelmont Innovation Campus (Belmont Ridge Road)
Loudoun County, Loudoun County
112 acres
π April 10, 2024: Board approved a 1.3 million-square-foot version, 6-3.
ProposedActive Infrastructure campus on Evergreen Mills Road
Loudoun County, Loudoun County
325 acres
π July 23, 2026: Planning Commission held a hearing and voted against the rezoning.
Stopped or cancelledOaklawn data center (Land Bay A, Leesburg)
Leesburg, Loudoun County
26.4 acres
π July 2025: Developer sued the town over the denial.
ProposedSTACK Infrastructure 144 MW Loudoun campus
Loudoun County, Loudoun County
π Feb 11, 2025: STACK announced the 144 MW campus.
Reported in the news, not confirmed yet
Being builtEdgeCore AS01 and AS02 data centers (Sterling)
Loudoun County, Loudoun County
π April 2026: EdgeCore secured $1.5 billion in loans to build AS01 and AS02.
Reported in the news, not confirmed yet
Local votes and rules
π Other Β· Loudoun County
Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.
βΈοΈ Pause on new data centers Β· Loudoun County
Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.
πΊοΈ Zoning change Β· Loudoun County
Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.
π Other Β· Loudoun County
On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.
β Approved Β· Loudoun County
Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.
Find your town
In Virginia, cities and towns decide inside their limits. Outside them, the county decides.