Greenlin Park data center campus (Dulles Greenway, south of Leesburg)
JK Land Holdings got approval to rezone 83 acres along the Dulles Greenway for 1.4 million square feet of data centers and a substation. Conditions include a 55-foot height limit, noise limits, water-use limits and a 300 MW power cap for five years.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Loudoun County Board of Supervisors (for land outside city and town limits).
Where things stand: Approved, not built yet Supervisors approved the rezoning in February 2025. Power use is capped at 300 MW for five years.
❓ 2 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Feb 19, 2025): Board of Supervisors approved the rezoning.
What we know
- 📍 WhereAlong the Dulles Greenway, south of Leesburg, Loudoun County, Loudoun County
- 🏢 CompanyJK Land Holdings
- 🌳 Size83 acres
- ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who will use the data center? 🙋 I'll find out ·
- Has construction started? 🙋 I'll find out ·
What happened so far
- July 2024Planning Commission recommended approval.
- Feb 19, 2025Board of Supervisors approved the rezoning.
Local votes and rules
📌 Other
The board put off its formal vote on the resolution to pause decisions on data center and substation applications for up to 12 months. The vote moved from October 20 to the board's November 17, 2026 meeting, so staff can gather more information. If passed, the pause would count back to September 15, 2026. Applications handled by staff alone are not affected.
📌 Other
After the county attorney warned that ending the 2025 grandfathering rule could lead to about $60 million in lawsuits, the board chair tabled the whole item, including a motion to hire an outside auditor to review data center projects one by one. Nothing was approved or denied, so the grandfathering rule stays in place for now.
📌 Other
Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.
⏸️ Pause on new data centers
Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.
🗺️ Zoning change
Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.
📌 Other
On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.
✅ Approved
Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.
Drag the slider to compare the land before and now.
Where this comes from
- 300 MW Data Center Approved South of Leesburg · Loudoun Now · Feb 20, 2025