Send us a tip
Approved, not built yet

Cross Mill Center data center (near Leesburg Executive Airport)

JK Land Holdings won a 5-4 vote to rezone 22 acres at Sycolin Road and Crosstrail Boulevard for up to 556,746 square feet of data centers. No substation is allowed on the site, and smaller power lines must be buried.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Loudoun County Board of Supervisors (for land outside city and town limits).

Where things stand: Approved, not built yet Supervisors approved the rezoning 5-4 in July 2025.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (July 15, 2025): Board of Supervisors approved the rezoning 5-4.

What we know

  • 📍 WhereCrosstrail Boulevard and Sycolin Road, near Leesburg Executive Airport, Loudoun County, Loudoun County
  • 🏢 CompanyJK Land Holdings
  • 🌳 Size22 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will use the data center? 🙋 I'll find out ·
  • How much power will it need, and from which substation? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 15, 2025
      Board of Supervisors approved the rezoning 5-4.

    Local votes and rules

    📌 Other

    The board put off its formal vote on the resolution to pause decisions on data center and substation applications for up to 12 months. The vote moved from October 20 to the board's November 17, 2026 meeting, so staff can gather more information. If passed, the pause would count back to September 15, 2026. Applications handled by staff alone are not affected.

    Oct 20, 2026

    📌 Other

    After the county attorney warned that ending the 2025 grandfathering rule could lead to about $60 million in lawsuits, the board chair tabled the whole item, including a motion to hire an outside auditor to review data center projects one by one. Nothing was approved or denied, so the grandfathering rule stays in place for now.

    Oct 6, 2026

    📌 Other

    Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.

    Sept 2, 2026

    ⏸️ Pause on new data centers

    Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.

    Sept 2026

    🗺️ Zoning change

    Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.

    March 18, 2025

    📌 Other

    On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.

    March 18, 2025

    ✅ Approved

    Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.

    Feb 19, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Supervisors Narrowly Approve Data Center Near Leesburg · Loudoun Now · July 16, 2025
    2. Proposal for data center in Leesburg, Virginia approved · DatacenterDynamics · July 2025

    See something wrong? Tell us and we'll fix it.