EdgeCore AS01 and AS02 data centers (Sterling)
EdgeCore is building two data centers on campuses about 2 miles apart in Loudoun County, 685,000 square feet and 114 MW in all. It raised $1.5 billion in loans for them in 2026. Both are leased to one big customer each.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Loudoun County Board of Supervisors (for land outside city and town limits).
Where things stand: Being built Fully leased. First building due to open November 2026, second July 2027.
❓ 1 open question about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (April 2026): EdgeCore secured $1.5 billion in loans to build AS01 and AS02.
What we know
- 📍 WhereAS01 at 45865 Maries Road, Sterling; AS02 at 1501 Moran Road, Sterling (pin is on AS01), Loudoun County, Loudoun County
- 🏢 CompanyEdgeCore Digital Infrastructure
- 🏛️ Owned byPartners Group
- ⚡ Power it needs114 megawatts (about as much as 91,200 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who are the tenants? 🙋 I'll find out ·
What happened so far
- April 2026EdgeCore secured $1.5 billion in loans to build AS01 and AS02.
Local votes and rules
📌 Other
The board put off its formal vote on the resolution to pause decisions on data center and substation applications for up to 12 months. The vote moved from October 20 to the board's November 17, 2026 meeting, so staff can gather more information. If passed, the pause would count back to September 15, 2026. Applications handled by staff alone are not affected.
📌 Other
After the county attorney warned that ending the 2025 grandfathering rule could lead to about $60 million in lawsuits, the board chair tabled the whole item, including a motion to hire an outside auditor to review data center projects one by one. Nothing was approved or denied, so the grandfathering rule stays in place for now.
📌 Other
Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.
⏸️ Pause on new data centers
Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.
🗺️ Zoning change
Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.
📌 Other
On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.
✅ Approved
Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.
Drag the slider to compare the land before and now.
Where this comes from
- EdgeCore secures $1.5B toward Sterling data centers construction · Virginia Business · April 22, 2026
- EdgeCore AS01 building outline · OpenStreetMap contributors (ODbL) · Oct 8, 2026
- EdgeCore plans new data center in Dulles area of Loudoun County · InsideNoVa · 2023
- Census geocoder: 45865 Maries Rd, Sterling · US Census Bureau · Oct 8, 2026
See something wrong? Tell us and we'll fix it.