No project in Middleburg Town, but 13 nearby
Who decides here: the Town Council of Middleburg Town votes on zoning. The Loudoun County may review big projects too.
Nearby (within 15 miles)
Quantum Park data centers (Ashburn)
Loudoun County, Loudoun County
40 acres
π April 15, 2026: Supervisors moved the plan to a May 19 vote; several said they would vote no.
Approved, not built yetabout 9 miles awayBelmont Innovation Campus (Belmont Ridge Road)
Loudoun County, Loudoun County
112 acres
π April 10, 2024: Board approved a 1.3 million-square-foot version, 6-3.
Proposedabout 9 miles awayActive Infrastructure campus on Evergreen Mills Road
Loudoun County, Loudoun County
325 acres
π July 23, 2026: Planning Commission held a hearing and voted against the rezoning.
Approved, not built yetabout 9 miles awayGreenlin Park data center campus (Dulles Greenway, south of Leesburg)
Loudoun County, Loudoun County
83 acres
π Feb 19, 2025: Board of Supervisors approved the rezoning.
Proposedabout 9 miles awaySTACK Infrastructure 144 MW Loudoun campus
Loudoun County, Loudoun County
π Feb 11, 2025: STACK announced the 144 MW campus.
Reported in the news, not confirmed yet
Being builtabout 9 miles awayEdgeCore AS01 and AS02 data centers (Sterling)
Loudoun County, Loudoun County
π April 2026: EdgeCore secured $1.5 billion in loans to build AS01 and AS02.
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Middleburg Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.