Quantum Park data centers (Ashburn)
A developer wants two new data center buildings and a substation on about 40 acres of the Quantum Park office campus at Loudoun County Parkway and Waxpool Road. The plan would remove a pond. Several supervisors called it too much and said they would vote against it.
Where things stand: Planning Commission recommended approval in February 2026. Several supervisors said in April they would vote no; a final vote was set for May 19, 2026.
π Latest update (April 15, 2026): Supervisors moved the plan to a May 19 vote; several said they would vote no.
What we know
- π WhereQuantum Park office campus, Loudoun County Parkway near Waxpool Road, Ashburn, Loudoun County, Loudoun County
- π³ Size40 acres
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- What did supervisors decide on May 19, 2026? π I'll find out
What happened so far
- Feb 12, 2026Planning Commission voted 7-1-1 to recommend approval.
- April 15, 2026Supervisors moved the plan to a May 19 vote; several said they would vote no.
Local votes and rules
π Other
Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.
βΈοΈ Pause on new data centers
Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.
πΊοΈ Zoning change
Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.
π Other
On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.
β Approved
Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.
An aerial photo of the area.
Where this comes from
- Planning Commission sends Quantum Park data center project to supervisors Β· Loudoun Times-Mirror Β· Feb 16, 2026