Belmont Innovation Campus (Belmont Ridge Road)
SDC Capital Partners, through Loudoun GC, first asked for 4.8 million square feet of data centers on about 112 acres between Belmont Ridge Road and Goose Creek. Supervisors denied a 2.9 million-square-foot version in March 2024, then approved 1.3 million square feet in April 2024 on a 6-3 vote.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Loudoun County Board of Supervisors (for land outside city and town limits).
Where things stand: Approved, not built yet Approved at a smaller size (1.3 million square feet) in April 2024 after a larger plan was denied.
❓ 1 open question about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (April 10, 2024): Board approved a 1.3 million-square-foot version, 6-3.
What we know
- 📍 WhereBetween Belmont Ridge Road and Goose Creek, southwest of Route 7, Loudoun County, Loudoun County
- 🏢 CompanyLoudoun GC (SDC Capital Partners)
- 🏛️ Owned bySDC Capital Partners
- 🌳 Size112 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who will use the campus, and has construction started? 🙋 I'll find out ·
What happened so far
- March 13, 2024Board of Supervisors denied a 2.9 million-square-foot version.
- April 10, 2024Board approved a 1.3 million-square-foot version, 6-3.
Local votes and rules
📌 Other
The board put off its formal vote on the resolution to pause decisions on data center and substation applications for up to 12 months. The vote moved from October 20 to the board's November 17, 2026 meeting, so staff can gather more information. If passed, the pause would count back to September 15, 2026. Applications handled by staff alone are not affected.
📌 Other
After the county attorney warned that ending the 2025 grandfathering rule could lead to about $60 million in lawsuits, the board chair tabled the whole item, including a motion to hire an outside auditor to review data center projects one by one. Nothing was approved or denied, so the grandfathering rule stays in place for now.
📌 Other
Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.
⏸️ Pause on new data centers
Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.
🗺️ Zoning change
Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.
📌 Other
On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.
✅ Approved
Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.
Drag the slider to compare the land before and now.
Where this comes from
- Smaller Belmont Innovation Data Center Campus Approved · Loudoun Now · April 11, 2024
- Board approves Belmont Innovation Campus (News Flash) · Loudoun County · April 2024
- Belmont Innovation Campus gets board approval from Loudoun County · DatacenterDynamics · April 2024