ProposedBig (AI-size): 325 acres

Active Infrastructure campus on Evergreen Mills Road

Also called: Ryan Road Hyperscale Site, Spring Valley Technology Park

Active Infrastructure wants to rezone 325 acres on Evergreen Mills Road, south of Watson Road, for 10 data center buildings (3.25 million square feet), three substations and energy storage. It promises cleaner generators, buried power lines and air cooling. At the July 2026 hearing, 50 people spoke against it and one for it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Loudoun County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed Planning Commission recommended denial in July 2026. The Board of Supervisors hearing set for October 14 was put off with no new date, at the developer's request.

❓ 2 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Oct 2026): The Board of Supervisors hearing set for October 14 was postponed with no new date, at the developer's request (reported by Loudoun Wildlife Conservancy).

What we know

  • 📍 WhereEast side of Evergreen Mills Road, south of Watson Road, Loudoun County, Loudoun County
  • 🏢 CompanyActive Infrastructure
  • 🌳 Size325 acres
  • 🗼 New power linesYes
  • ❄️ Coolingair cooling (promised)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the Board of Supervisors vote on it, or will the developer withdraw? 🙋 I'll find out ·
  • When will the Board of Supervisors hold its hearing on Spring Valley Technology Park? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 23, 2026
      Planning Commission held a hearing and voted against the rezoning.
    • Oct 2026
      The Board of Supervisors hearing set for October 14 was postponed with no new date, at the developer's request (reported by Loudoun Wildlife Conservancy).

    Local votes and rules

    📌 Other

    The board put off its formal vote on the resolution to pause decisions on data center and substation applications for up to 12 months. The vote moved from October 20 to the board's November 17, 2026 meeting, so staff can gather more information. If passed, the pause would count back to September 15, 2026. Applications handled by staff alone are not affected.

    Oct 20, 2026

    📌 Other

    After the county attorney warned that ending the 2025 grandfathering rule could lead to about $60 million in lawsuits, the board chair tabled the whole item, including a motion to hire an outside auditor to review data center projects one by one. Nothing was approved or denied, so the grandfathering rule stays in place for now.

    Oct 6, 2026

    📌 Other

    Supervisors voted unanimously to ask staff for a legal analysis of ending the 2025 grandfathering rule, due at the October 6, 2026 board meeting. Until the board acts, the rule stays in effect.

    Sept 2, 2026

    ⏸️ Pause on new data centers

    Supervisors voted 7-1 to pause new data center applications for 12 months while the county rewrites its data center rules. The county attorney had warned that true moratoria are rarely allowed in Virginia.

    Sept 2026

    🗺️ Zoning change

    Supervisors voted 7-2 to end by-right data centers. New data centers now need a 'special exception', with public hearings before the planning commission and the board.

    March 18, 2025

    📌 Other

    On the same night, supervisors voted 5-4 to 'grandfather' data center applications already in review, so they can still be approved by staff without a public hearing. In September 2026, 17 such applications (about 11 million square feet) were still in review.

    March 18, 2025

    ✅ Approved

    Supervisors voted 5-4 to rezone 83 acres south of Leesburg along the Dulles Greenway for JK Land Holdings' Greenlin Park: up to 1.4 million square feet of data centers with a 55-foot height limit, noise limits and a 300-megawatt power cap for five years.

    Feb 19, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Loudoun Planning Commission Rejects 3M-Square-Foot Data Center Campus · Loudoun Now · July 24, 2026
    2. Loudoun Data Center Advocacy Happenings October 2026 · Loudoun Wildlife Conservancy · Oct 1, 2026
    3. Spring Valley Planning Commission testimony (July 2026) · Loudoun Wildlife Conservancy · July 20, 2026

    See something wrong? Tell us and we'll fix it.