Being builtBig (AI-size): 600 megawatts

NTT Grove at Gainesville campus (I-66 and U.S. 29)

Also called: The Grove at Gainesville

NTT Global Data Centers is building four data centers of about 550,000 square feet each near I-66 and U.S. 29 in Gainesville. The first is the biggest data center building in the county. At full use the campus would draw as much power as 150,000 homes.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Prince William County Board of Supervisors (for land outside city and town limits).

Where things stand: Being built First of four buildings was going up in 2024.

❓ 1 open question about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (July 2024): First building was rising along I-66.

What we know

  • 📍 Where14300 John Marshall Highway, Gainesville (I-66 and U.S. 29), Prince William County, Prince William County
  • 🏢 CompanyNTT Global Data Centers
  • 🌳 Size102 acres
  • ⚡ Power it needs600 megawatts (about as much as 480,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many of the four buildings are finished? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2024
      First building was rising along I-66.

    Local votes and rules

    🗺️ Zoning change

    Supervisors unanimously shrank the Data Center Opportunity Zone Overlay District from about 9,700 to 3,500 acres. Most new data centers will now need a special use permit with a public hearing. Projects already filed get a 90-day grace period.

    Sept 22, 2026

    ✋ Turned down

    Supervisors voted 8-0 to reject a land-use plan change for the Dulles South Innovation Center, a proposed campus of about 43 million square feet of data centers on 1,940 acres of homes and farms near Sanders Lane (Gainesville District).

    July 7, 2026

    ⚖️ Court case

    Neighbors sued over the county's December 2023 rezoning for the 2,100-acre Prince William Digital Gateway. A judge voided it because the newspaper notices were not spaced far enough apart, and the Court of Appeals agreed on March 31, 2026. The county stopped defending it in April, and QTS dropped its last appeal on July 2, 2026, ending the project.

    March 31, 2026

    📜 Data center rules

    Supervisors voted 5-2 to update the noise law so data center cooling systems must meet noise limits around the clock: 73 decibels by day and 68 at night, measured on the 'C' scale that captures low hum. Residents and the county's advisory group had asked for a stricter method.

    Oct 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. County's largest data center — so far — rises along I-66 · Prince William Times · July 25, 2024
    2. NTT VA10 building outline · OpenStreetMap contributors (ODbL) · Oct 8, 2026
    3. NTT Global Data Centers VA10, 14300 John Marshall Highway · datacenterHawk · Oct 8, 2026
    4. Census geocoder: 14300 John Marshall Hwy · US Census Bureau · Oct 8, 2026