No project in Hamilton Town, but 11 nearby
Who decides here: the Town Council of Hamilton Town votes on zoning. The Loudoun County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Cross Mill Center data center (near Leesburg Executive Airport)
Loudoun County, Loudoun County
22 acres
🕒 July 15, 2025: Board of Supervisors approved the rezoning 5-4.
Approved, not built yetabout 4 miles awayGreenlin Park data center campus (Dulles Greenway, south of Leesburg)
Loudoun County, Loudoun County
83 acres
🕒 Feb 19, 2025: Board of Supervisors approved the rezoning.
Proposedabout 4 miles awayCochran Tech data center (Cochran Mill Road, near Leesburg)
Loudoun County, Loudoun County
17.52 acres
🕒 May 5, 2026: Board voted 6-1-1 to reconsider and send the plan back to the Planning Commission.
Proposedabout 4 miles awayQuantum Park data centers (Ashburn)
Loudoun County, Loudoun County
40 acres
🕒 April 15, 2026: Supervisors moved the plan to a May 19 vote; several said they would vote no.
Proposedabout 4 miles awayB.F. Saul data centers on Shaw Road (Sterling)
Loudoun County, Loudoun County
37.24 acres
🕒 Sept 2026: Loudoun Planning Commission voted against the rezoning.
Approved, not built yetabout 4 miles awayBelmont Innovation Campus (Belmont Ridge Road)
Loudoun County, Loudoun County
112 acres
🕒 April 10, 2024: Board approved a 1.3 million-square-foot version, 6-3.
Proposedabout 4 miles awayActive Infrastructure campus on Evergreen Mills Road
Loudoun County, Loudoun County
325 acres
🕒 Oct 2026: The Board of Supervisors hearing set for October 14 was postponed with no new date, at t…
Proposedabout 4 miles awaySTACK Infrastructure 144 MW Loudoun campus
Loudoun County, Loudoun County
🕒 Feb 11, 2025: STACK announced the 144 MW campus.
Reported in the news, not confirmed yet
Proposedabout 7 miles awayLeesburg Gateway data center plan (Peterson Companies)
Leesburg, Loudoun County
107 acres
🕒 Jan 26, 2026: Town Council cancelled its public hearing at the developer's request.
Proposedabout 13 miles awayAmazon Bridgefield Tech Center (former GW Virginia campus, Ashburn)
Loudoun County, Loudoun County
122 acres · for Amazon Web Services
🕒 July 28, 2026: Amazon filed a first plan for four data center buildings (805,092 square feet).
What you can do
- Get told first.
We'll email you if anything changes in Hamilton Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.