USA β€Ί Pennsylvania β€Ί Lackawanna County β€Ί Archbald Borough

8 data center projects in Archbald Borough

Who decides here: the Borough Council of Archbald Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.

In Archbald Borough

Proposed

Wildcat Ridge data center campus (Archbald)

Archbald, Lackawanna County

574 acres

πŸ•’ Sept 10, 2026: Council refused to step aside (recusal) and closed the hearing record after 9 hearings.

Proposed

Project Gravity (Archbald)

Archbald, Lackawanna County

186 acres Β· for A future hyperscale tenant (not named)

πŸ•’ Sept 22, 2026: Corscale (owner since Dec. 2025) said final land development plans would be submitted so…

Proposed

Project Green Mountain (Archbald)

Archbald, Lackawanna County

271 acres

πŸ•’ Sept 30, 2026: Hearings set to resume.

Proposed

Project Boson (Archbald)

Archbald, Lackawanna County

86 acres

πŸ•’ Dec 2025: Plan merged into one building of about 620,000 square feet ('Project Boson').

Proposed

Project Scott (Archbald I LLC, 18 buildings)

Archbald, Lackawanna County

400 acres

πŸ•’ Sept 18, 2026: The Times-Tribune listed Project Scott as denied by Archbald Council and in court agains…

Proposed

Project North (Archbald I LLC, 4 buildings near the Jermyn line)

Archbald, Lackawanna County

66 acres

πŸ•’ Sept 18, 2026: The Times-Tribune listed 'Project North' (4 buildings, 66 acres) as applied under Archba…

Status unclear

DBT-Data Lackawanna Two, Three and Four sites (Archbald/Jessup)

Archbald, Lackawanna County

355 acres

πŸ•’ Sept 2026: Reported that DBT holds memorandums with SLIBCO for three more sites.

Reported in the news, not confirmed yet

Status unclear

PNK Group data centers (Valley View Business Park, Archbald)

Archbald, Lackawanna County

89 acres

πŸ•’ July 2026: PNK began a mail and online campaign about two data centers.

Reported in the news, not confirmed yet

Nearby (within 15 miles)

πŸ—“οΈ Next meeting of the people who decide: Oct 21, 2026 Β· 7:00 PM
Archbald Borough Council. We don't know yet if Wildcat Ridge data center campus (Archbald) is on the agenda. Call the office to check before you go.
Written decision on the Wildcat Ridge conditional use is due by about Oct. 25.
πŸ“ Archbald Borough Council meets the third Wednesday of each month at 7 p.m. in Council Chambers, Borough Municipal Building, 400 Church Street, Archbald. Big data center hearings have been moved to Valley View High School, 1 Columbus Drive, so check the borough website or Facebook page first. The council said it would announce the day it votes; it may call a special meeting instead.

Local votes and rules

πŸ“Œ Other

Archbald Borough Council finished hearings on the Wildcat Ridge data center campus, which would have 14 large buildings on more than 500 acres. Council refused the developer's request that members step aside for bias. A written decision is due within 45 days of the last hearing.

Sept 10, 2026Source

πŸ“Œ Other Β· Lackawanna County

Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.

Sept 2026Source

βœ‹ Turned down

Archbald Borough Council voted down a plan by Texas-based Provident Realty Advisors (Archbald 1 LLC) for a data center complex with 18 computer buildings. About 200 residents came to the special meeting to oppose it.

March 27, 2026Source

πŸ“Œ Other

After months of complaints about how data center plans were handled, Archbald Borough Council removed its president, vice president, and president pro tem from those leadership roles. A new council president was chosen.

March 18, 2026Source

βš–οΈ Court case

Eight Archbald residents asked the county court to throw out the borough's new data center zoning law. They say the borough skipped required steps like proper notice and planning review. They also say the law lets data centers go in more places and be taller and louder.

Dec 23, 2025Source

πŸ“œ Data center rules

Archbald Borough Council voted 4-2, with one member not voting, to add data center rules to its zoning law. The rules create data center overlay zones in four areas of the borough. Many residents spoke against it, and an earlier try in October failed.

Nov 24, 2025Source

πŸ“Œ Other

Archbald Borough Council met to vote on new data center zoning rules, but the plan died because no one seconded the motion. Residents saw this as a win. Council later passed the rules in November 2025.

Oct 3, 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Archbald Borough.
  2. Go to borough meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Archbald Borough. Nothing else.

⚑ Your electric company

PPL Electric Utilities Corp. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.

πŸ™‹ Open tasks here

  • Who is the end user (tenant)?
  • How much water will it really use each day, and from where?
  • Will new high-voltage power lines be built, and who pays for them?
  • Was a secret deal (NDA) signed with any official?
  • On what date will Borough Council vote?
  • Will the Wildcat Ridge developer apply to the Susquehanna River Basin Commission to use mine pool water, and who pays for the $93 million in water upgrades?
  • Who is the tenant?
  • How many megawatts of power will it use?
  • Has it applied for an air permit for its diesel generators?
  • Why was it removed from the state Fast Track program?
  • Was a secret deal (NDA) signed?
  • Has Project Gravity applied to the Susquehanna River Basin Commission? (Water lost to evaporation above 20,000 gallons a day needs SRBC approval.)
  • Who is the end user?
  • Who owns Green Mountain 6 LLC?
  • How loud will 196 diesel generators be for neighbors?
  • When will hearings end and council vote?
  • Was a secret deal (NDA) signed?
  • What is the current approval status?
  • How much power and water will it use?
  • Who is the end user?
  • What will the court decide on the appeal?
  • Is a second application under the older 2023 zoning still alive?
  • Who would the end user be?
  • How much power and water would it use?
  • When will Archbald decide on the Project North zoning permits?
  • Has DBT filed any plans for these sites?
  • Did SLIBCO or the county sign a secret deal (NDA)?
  • Has PNK filed a data center application?
  • How much power and water would it use?