PNK Group data centers (Valley View Business Park, Archbald)
Also called: PNK Park Valley View
PNK Group bought about 89 acres in the Valley View Business Park in 2024 for warehouses. In 2026 it began asking residents about building two data centers there instead.
Where things stand: Developer ran mailers and online ads in July 2026 asking residents about two data centers. No application found.
๐ Latest update (July 2026): PNK began a mail and online campaign about two data centers.
Archbald Borough Council. We don't know yet if PNK Group data centers (Valley View Business Park, Archbald) is on the agenda. Call the office to check before you go.
What we know
- ๐ WhereValley View Business Park, east of the Casey Highway, Archbald, Lackawanna County
- ๐ข CompanyPNK Group (New York)
- ๐ณ Size89 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has PNK filed a data center application? ๐ I'll find out
- How much power and water would it use? ๐ I'll find out
๐ What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
What happened so far
- March 20, 2024PNK bought about 89 acres in Jessup and Archbald for industrial buildings.
- July 2026PNK began a mail and online campaign about two data centers.
Local votes and rules
๐ Other
Archbald Borough Council finished hearings on the Wildcat Ridge data center campus, which would have 14 large buildings on more than 500 acres. Council refused the developer's request that members step aside for bias. A written decision is due within 45 days of the last hearing.
โ Turned down
Archbald Borough Council voted down a plan by Texas-based Provident Realty Advisors (Archbald 1 LLC) for a data center complex with 18 computer buildings. About 200 residents came to the special meeting to oppose it.
๐ Other
After months of complaints about how data center plans were handled, Archbald Borough Council removed its president, vice president, and president pro tem from those leadership roles. A new council president was chosen.
โ๏ธ Court case
Eight Archbald residents asked the county court to throw out the borough's new data center zoning law. They say the borough skipped required steps like proper notice and planning review. They also say the law lets data centers go in more places and be taller and louder.
๐ Data center rules
Archbald Borough Council voted 4-2, with one member not voting, to add data center rules to its zoning law. The rules create data center overlay zones in four areas of the borough. Many residents spoke against it, and an earlier try in October failed.
๐ Other
Archbald Borough Council met to vote on new data center zoning rules, but the plan died because no one seconded the motion. Residents saw this as a win. Council later passed the rules in November 2025.
Drag the slider to compare the land before and now.
Where this comes from
- PNK Group USA Announces PNK Park Valley View Will Be Built in Pennsylvania ยท PNK Group (press release) ยท March 20, 2024
- Archbald's latest data center suitor distances itself from Russian origins ยท AllSides (headline of Times-Tribune story) ยท Aug 2, 2026
- Project Green Mountain hearings to resume in Archbald this month ยท The Times-Tribune (via Yahoo News) ยท Sept 2026
- Officials & Government (meeting schedule) ยท Archbald Borough ยท Oct 6, 2026
- Water Use by Data Centers in the Susquehanna River Basin - FAQ ยท Susquehanna River Basin Commission ยท 2026
- Water Application and Approval Viewer (WAAV) ยท Susquehanna River Basin Commission ยท Oct 6, 2026
See something wrong? Tell us and we'll fix it.