Proposed

Project North (Archbald I LLC, 4 buildings near the Jermyn line)

Also called: Project North, Archbald I LLC campus 2, Unnamed Data Centers (Archbald I LLC / Archbald II LLC), Archbald II LLC, Provident Data Centers

A smaller four-building data center campus on about 66 acres near the Archbald-Jermyn border, filed by the same company behind Project Scott. Its current status is not clear.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Applied for zoning permits in Oct. 2025 under the borough's older rules, which allowed data centers as a permitted use. No decision reported. DEP lists it with no state permit applications yet.

๐Ÿ•’ Latest update (Sept 18, 2026): The Times-Tribune listed 'Project North' (4 buildings, 66 acres) as applied under Archbald's older zoning, where data centers were a permitted use.

๐Ÿ—“๏ธ Next meeting of the people who decide: Oct 21, 2026 ยท 7:00 PM
Archbald Borough Council. We don't know yet if Project North (Archbald I LLC, 4 buildings near the Jermyn line) is on the agenda. Call the office to check before you go.
๐Ÿ“ Archbald Borough Council meets the third Wednesday of each month at 7 p.m. in Council Chambers, Borough Municipal Building, 400 Church Street, Archbald. Big data center hearings have been moved to Valley View High School, 1 Columbus Drive, so check the borough website or Facebook page first.

What we know

  • ๐Ÿ“ WhereBetween Business Route 6 and Eynon Jermyn Road in Archbald, near Lackawanna and Gibson streets in Jermyn, Archbald, Lackawanna County
  • ๐Ÿข CompanyArchbald I LLC (Provident Realty Advisors of Dallas, operating as Provident Data Centers)
  • ๐Ÿ›๏ธ Owned byProvident Realty Advisors (Texas)
  • ๐ŸŒณ Size66 acres

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

๐Ÿ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • Oct 22, 2025
    Zoning permit application filed.
  • Sept 18, 2026
    The Times-Tribune listed 'Project North' (4 buildings, 66 acres) as applied under Archbald's older zoning, where data centers were a permitted use.

Local votes and rules

๐Ÿ“Œ Other

Archbald Borough Council finished hearings on the Wildcat Ridge data center campus, which would have 14 large buildings on more than 500 acres. Council refused the developer's request that members step aside for bias. A written decision is due within 45 days of the last hearing.

Sept 10, 2026

โœ‹ Turned down

Archbald Borough Council voted down a plan by Texas-based Provident Realty Advisors (Archbald 1 LLC) for a data center complex with 18 computer buildings. About 200 residents came to the special meeting to oppose it.

March 27, 2026

๐Ÿ“Œ Other

After months of complaints about how data center plans were handled, Archbald Borough Council removed its president, vice president, and president pro tem from those leadership roles. A new council president was chosen.

March 18, 2026

โš–๏ธ Court case

Eight Archbald residents asked the county court to throw out the borough's new data center zoning law. They say the borough skipped required steps like proper notice and planning review. They also say the law lets data centers go in more places and be taller and louder.

Dec 23, 2025

๐Ÿ“œ Data center rules

Archbald Borough Council voted 4-2, with one member not voting, to add data center rules to its zoning law. The rules create data center overlay zones in four areas of the borough. Many residents spoke against it, and an earlier try in October failed.

Nov 24, 2025

๐Ÿ“Œ Other

Archbald Borough Council met to vote on new data center zoning rules, but the plan died because no one seconded the motion. Residents saw this as a win. Council later passed the rules in November 2025.

Oct 3, 2025
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

2018โ€“20202021โ€“2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Archbald I LLC: Campus 2 ยท Baxtel (tracker)
  2. Data centers as 2025 newsmaker of the year ยท The Times-Tribune (via Yahoo News) ยท Dec 28, 2025
  3. Officials & Government (meeting schedule) ยท Archbald Borough ยท Oct 6, 2026
  4. 22 regional data center projects and where they stand ยท The Times-Tribune ยท Sept 18, 2026
  5. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) ยท Pennsylvania DEP ยท Oct 6, 2026
  6. Water Use by Data Centers in the Susquehanna River Basin - FAQ ยท Susquehanna River Basin Commission ยท 2026
  7. Water Application and Approval Viewer (WAAV) ยท Susquehanna River Basin Commission ยท Oct 6, 2026
  8. Data Centers Are Poised to Engulf a Pennsylvania Town ยท DeSmog ยท March 11, 2026