Proposed

Project Green Mountain (Archbald)

Also called: Green Mountain 6 LLC

A developer wants seven data center buildings on about 271 acres of quarry land in Archbald, using 525 megawatts of power. It says it would use up to 14,000 gallons of water a day. Borough Council is holding hearings and must vote within 45 days after they end.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Conditional use hearings before Borough Council; hearings resumed Sept. 30, 2026.

๐Ÿ•’ Latest update (Sept 30, 2026): Hearings set to resume.

๐Ÿ—“๏ธ Public meeting: Oct 21, 2026 ยท 7:00 PM
Archbald Borough Council (regular meeting). The Green Mountain conditional use hearing's next session after Sept. 30 has not been announced.. Anyone can come and speak.
๐Ÿ“ Archbald Borough Council meets the third Wednesday of each month at 7 p.m. in Council Chambers, Borough Municipal Building, 400 Church Street, Archbald. Big data center hearings have been moved to Valley View High School, 1 Columbus Drive, so check the borough website or Facebook page first. Past Green Mountain hearing sessions were at 5 p.m. at Valley View High School auditorium, 1 Columbus Drive; public comment comes after all witnesses testify.

What we know

  • ๐Ÿ“ WhereStavola quarry land east of the Casey Highway (Route 6), Archbald, Lackawanna County
  • ๐Ÿข CompanyGreen Mountain 6 LLC
  • ๐ŸŒณ Size271 acres
  • โšก Power it needs525 megawatts (about as much as 420,000 homes)
  • ๐Ÿ”Œ Where the power comes fromGrid power; 196 diesel backup generators with about 1.96 million gallons of fuel stored on site
  • ๐Ÿ’ง WaterPennsylvania American Water ยท 14,000 gallons a day
  • โ„๏ธ CoolingClosed-loop system with water and glycol (delivered by truck)
  • ๐Ÿ›ข๏ธ Diesel generators196

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

๐Ÿ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • March 19, 2026
    First conditional use hearing.
  • June 18, 2026
    Hearing held; then a three-month break.
  • Sept 30, 2026
    Hearings set to resume.

Local votes and rules

๐Ÿ“Œ Other

Archbald Borough Council finished hearings on the Wildcat Ridge data center campus, which would have 14 large buildings on more than 500 acres. Council refused the developer's request that members step aside for bias. A written decision is due within 45 days of the last hearing.

Sept 10, 2026

โœ‹ Turned down

Archbald Borough Council voted down a plan by Texas-based Provident Realty Advisors (Archbald 1 LLC) for a data center complex with 18 computer buildings. About 200 residents came to the special meeting to oppose it.

March 27, 2026

๐Ÿ“Œ Other

After months of complaints about how data center plans were handled, Archbald Borough Council removed its president, vice president, and president pro tem from those leadership roles. A new council president was chosen.

March 18, 2026

โš–๏ธ Court case

Eight Archbald residents asked the county court to throw out the borough's new data center zoning law. They say the borough skipped required steps like proper notice and planning review. They also say the law lets data centers go in more places and be taller and louder.

Dec 23, 2025

๐Ÿ“œ Data center rules

Archbald Borough Council voted 4-2, with one member not voting, to add data center rules to its zoning law. The rules create data center overlay zones in four areas of the borough. Many residents spoke against it, and an earlier try in October failed.

Nov 24, 2025

๐Ÿ“Œ Other

Archbald Borough Council met to vote on new data center zoning rules, but the plan died because no one seconded the motion. Residents saw this as a win. Council later passed the rules in November 2025.

Oct 3, 2025
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

2018โ€“20202021โ€“2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Project Green Mountain hearings to resume in Archbald this month ยท The Times-Tribune (via Yahoo News) ยท Sept 2026
  2. Data Centers Are Poised to Engulf a Pennsylvania Town ยท DeSmog ยท March 11, 2026
  3. PA DEP Data Center Permit Tracker ยท Pennsylvania DEP ยท Oct 6, 2026
  4. Officials & Government (meeting schedule) ยท Archbald Borough ยท Oct 6, 2026
  5. Archbald residents pack Valley View High School for Project Green Mountain hearing ยท FOX56 (WOLF-TV) ยท March 19, 2026
  6. Water Use by Data Centers in the Susquehanna River Basin - FAQ ยท Susquehanna River Basin Commission ยท 2026
  7. Water Application and Approval Viewer (WAAV) ยท Susquehanna River Basin Commission ยท Oct 6, 2026

See something wrong? Tell us and we'll fix it.