Project Gravity (Archbald)
Also called: Archbald 25 Developer LLC, US Gravity Purchaser LLC, Corscale, Western Hospitality Partners - Jermyn LLC
Data center company Corscale now owns this 186-acre old mine site in Archbald and plans seven two-story data center buildings for a future large tenant. It says the project is worth $5 billion and would use about 360,000 gallons of water a day. It still needs state permits and final borough approval.
What happens next?
🗓️ Next meeting of the people who decide: Wednesday, November 18, 2026 (time not announced)
Archbald Borough Council meeting
📍 Council's regular meeting is the third Wednesday of each month. The borough's 2026 council meetings were Jan. 21, Feb. 18, March 18, April 15, May 20, June 17, July 15, Aug. 19, Sept. 16 and Oct. 21. Check the agenda on the borough website for the time and place.
Regular monthly meeting (third Wednesday). No agenda is posted yet, and this project is not known to be on it.
The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Allowed under Archbald's older zoning; conditional preliminary plan approval Sept. 2025. Corscale says it filed final land development plans with the borough in Sept. 2026. No final approval yet.
❓ 7 open questions about it: see below.
Last checked Nov 9, 2026.
🕒 Latest update (Oct 2026): Corscale held an open house at the borough building. It said the campus would be 475 megawatts in seven buildings, cost $8.4 billion, use closed-loop cooling and about 7,500 gallons of water a day, and use a large battery system so it needs 45 generators instead of 260. It said it has a tenant but would not name it and has not asked for tax breaks.
What we know
- 📍 WhereAbout 186 acres between Business Route 6 and Eynon Jermyn Road, next to State Game Lands 307 and Valley View Estates, Archbald, Lackawanna County
- 🏢 CompanyCorscale (US Gravity Purchaser LLC); earlier Archbald 25 Developer LLC
- 🏛️ Owned byCorscale
- 👤 Built forA future hyperscale tenant (not named)
- 🌳 Size186 acres
- ⚡ Power it needs475 megawatts (about as much as 380,000 homes)
- 🔌 Where the power comes fromNext to a high-voltage power line; on-site substation planned; diesel backup generators
- 💧 WaterPennsylvania American Water (Lake Scranton) · 360,000 gallons a day
- ❄️ Coolingclosed-loop cooling (developer, Oct. 2026)
- 💵 Cost$8.4 billion
- 👷 Jobs promised300
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the tenant? 🙋 I'll find out ·
- Has it applied for an air permit for its diesel generators? 🙋 I'll find out ·
- Why was it removed from the state Fast Track program? 🙋 I'll find out ·
- Was an agreement to keep the plans private (NDA) signed? 🙋 I'll find out ·
- Has Project Gravity applied to the Susquehanna River Basin Commission? (Water lost to evaporation above 20,000 gallons a day needs SRBC approval.) 🙋 I'll find out ·
- In January 2026 the developer estimated 360,000 gallons of water a day; in October 2026 Corscale said about 7,500 gallons a day. Which number is right for the final plan? 🙋 I'll find out ·
- When will Archbald Borough Council vote on Project Gravity's final land development plan? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
What happened so far
- Sept 2025Planning Commission gave conditional preliminary plan approval.
- Sept 22, 2025Accepted into the state's PA Permit Fast Track program.
- Jan 8, 2026DEP public meeting on water and earth-moving permits; developer said it had no tenant.
- Jan 8, 2026At a DEP meeting, the developer estimated 360,000 gallons of water a day from Pennsylvania American Water's Lake Scranton reservoir; the water company said it can supply that much. Cooling type will depend on the tenant. Wastewater would go to the Lackawanna River Basin Sewer Authority.
- March 2026Trees on the site were cleared.
- May 1, 2026Governor's office removed it from Fast Track for not being responsive or transparent.
- Sept 2026Corscale said it submitted final land development plans to Archbald Borough.
- Sept 22, 2026Corscale (owner since Dec. 2025) said final land development plans would be submitted soon.
- Oct 2026Corscale held an open house at the borough building. It said the campus would be 475 megawatts in seven buildings, cost $8.4 billion, use closed-loop cooling and about 7,500 gallons of water a day, and use a large battery system so it needs 45 generators instead of 260. It said it has a tenant but would not name it and has not asked for tax breaks.
Local votes and rules
📌 Other
Archbald Borough Council finished hearings on the Wildcat Ridge data center campus, which would have 14 large buildings on more than 500 acres. Council refused the developer's request that members step aside for bias. A written decision is due within 45 days of the last hearing.
✋ Turned down
Archbald Borough Council voted down a plan by Texas-based Provident Realty Advisors (Archbald 1 LLC) for a data center complex with 18 computer buildings. About 200 residents came to the special meeting to oppose it.
📌 Other
After months of complaints about how data center plans were handled, Archbald Borough Council removed its president, vice president, and president pro tem from those leadership roles. A new council president was chosen.
⚖️ Court case
Eight Archbald residents asked the county court to throw out the borough's new data center zoning law. They say the borough skipped required steps like proper notice and planning review. They also say the law lets data centers go in more places and be taller and louder.
📜 Data center rules
Archbald Borough Council voted 4-2, with one member not voting, to add data center rules to its zoning law. The rules create data center overlay zones in four areas of the borough. Many residents spoke against it, and an earlier try in October failed.
📌 Other
Archbald Borough Council met to vote on new data center zoning rules, but the plan died because no one seconded the motion. Residents saw this as a win. Council later passed the rules in November 2025.
Drag the slider to compare the land before and now.
Where this comes from
- Data center developer joins workforce panel, discusses Project Gravity in Archbald · WVIA · Sept 22, 2026
- No tenant yet: Archbald data center developer answers questions about project applications at DEP meeting · WVIA · Jan 8, 2026
- Fast track no more: Pa. kicks Archbald data center campus off permit program · WVIA · May 1, 2026
- Data Centers Are Poised to Engulf a Pennsylvania Town · DeSmog · March 11, 2026
- Data centers as 2025 newsmaker of the year · The Times-Tribune (via Yahoo News) · Dec 28, 2025
- PA DEP Data Center Permit Tracker · Pennsylvania DEP · Oct 6, 2026
- Officials & Government (meeting schedule) · Archbald Borough · Oct 6, 2026
- Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
- Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
- Archbald residents: Still skeptical after open house for the Project Gravity Data Center Campus · WVIA · Oct 15, 2026
- Agendas & Minutes · Archbald Borough · Oct 26, 2026