12 data center projects we know about. 41 townships, villages and cities.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

Projects

Being built

Cologix AI data center campus (Johnstown)

Johnstown, Licking County

154 acres

πŸ•’ Sept 10, 2026: Johnstown City Council set a Jan. 5, 2027 special election on a charter ban of data cent…

Proposed

Karis Critical 'Smart Farms' data center campus (Beech and Green Chapel roads)

New Albany, Licking County

114 acres

πŸ•’ Jan 2026: Karis asked Ohio EPA for permission to fill wetlands and streams on the site.

Reported in the news, not confirmed yet

Being built

Microsoft data center on Thornwood Drive (Heath)

Heath, Licking County

for Microsoft

πŸ•’ Sept 2026: Heath officials rejected the petition, saying it lacked valid signatures; petitioners di…

Being built

Microsoft data center (Hebron)

Hebron, Licking County

for Microsoft

πŸ•’ Nov 13, 2025: Microsoft said site work had started in Hebron, with Ames Construction as general contra…

Proposed

Microsoft land on Refugee Road (Pataskala)

Pataskala, Licking County

for Microsoft

πŸ•’ Aug 25, 2026: Local reporting described a Microsoft data center as proposed for the Refugee Road site.

Reported in the news, not confirmed yet

Stopped or cancelled

Aligned Data Centers plan in Pataskala Corporate Park

Pataskala, Licking County

89 acres

πŸ•’ Aug 25, 2026: City council voted 7-0 to reject the site plan, citing missing power details.

Being built

Vantage Data Centers OH1 campus (New Albany)

New Albany, Licking County

70 acres

πŸ•’ Oct 25, 2024: Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.

Reported in the news, not confirmed yet

Being built

EdgeConneX data center campus on Innovation Campus Way (New Albany)

New Albany, Licking County

πŸ•’ April 10, 2026: A case for a third, 430 MW gas plant was opened with the Power Siting Board.

Being built

Meta data center campus expansion (New Albany, 'Prometheus')

New Albany, Licking County

574 acres Β· for Meta

πŸ•’ Aug 2026: The 200 MW 'Socrates South' gas plant near Beech and Morse roads began running.

Built & running

AWS $3.5 billion data center campus (New Albany)

New Albany, Licking County

for Amazon Web Services

πŸ•’ Aug 7, 2025: City and AWS said two buildings were finished and the rest were under construction.

Being built

CyrusOne data center on Jug Street Road (New Albany)

New Albany, Licking County

πŸ•’ Sept 2025: CyrusOne held a groundbreaking.

Proposed

Google land on Harrison Road NW (New Albany)

New Albany, Licking County

85 acres Β· for Google

πŸ•’ May 2025: A Google company bought about 85 acres for $63 million.

Local votes and rules

πŸ—³οΈ Public vote Β· Granville

Voters will decide a charter change that would ban data centers that use more than 25 megawatts of power.

Nov 3, 2026Source

πŸ—³οΈ Public vote Β· Pataskala

Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. City council had earlier rejected a data center proposal.

Nov 3, 2026Source

⏸️ Pause on new data centers · Buckeye Lake

Village council passed a one-year pause (moratorium) on new data centers. It is set to end in July 2027.

July 2026Source

🚫 Ban · St. Albans

Township trustees passed a zoning change that in effect bans data centers. News reports called it the first ban in Licking County.

March 2026Source