Microsoft restarted its Hebron data center after pausing it in 2025. Crews cleared trees and are grading the land in 2026, with a substation planned. Microsoft has not shared its size, power or water use.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Mass grading set for February to November 2026, then the building itself.

๐Ÿ•’ Latest update (Nov 13, 2025): Microsoft said site work had started in Hebron, with Ames Construction as general contractor.

What we know

  • ๐Ÿ“ WhereNext to Thomas J. Evans Park and the industrial park; construction entrance off Canyon Road, Hebron, Licking County
  • ๐Ÿข CompanyMicrosoft
  • ๐Ÿ‘ค Built forMicrosoft

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Oct 2024
    Microsoft announced data centers in New Albany, Hebron and Heath.
  • April 2025
    Microsoft paused its Licking County plans.
  • Nov 13, 2025
    Microsoft said site work had started in Hebron, with Ames Construction as general contractor.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Hebron datacenter construction update ยท Microsoft ยท Nov 13, 2025
  2. Microsoft Hits Pause Button on $1B in Data Centers in Ohio ยท Engineering News-Record ยท April 10, 2025

See something wrong? Tell us and we'll fix it.