USA › Ohio › Licking County › Johnstown City

1 data center project in Johnstown City

Who decides here: the City Council of Johnstown City votes on zoning. The Licking County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Johnstown City

Nearby (within 15 miles)

Being builtabout 3 miles away

Meta data center campus expansion (New Albany, 'Prometheus')

New Albany, Licking County

574 acres · for Meta

🕒 Oct 2026: The Ohio Power Siting Board heard public comments on a proposed fourth gas power plant t…

Proposedabout 4 miles away

Karis Critical 'Smart Farms' data center campus (Beech and Green Chapel roads)

New Albany, Licking County

114 acres

🕒 Jan 2026: Karis asked Ohio EPA for permission to fill wetlands and streams on the site.

Reported in the news, not confirmed yet

Proposedabout 4 miles away

Google land on Harrison Road NW (New Albany)

New Albany, Licking County

85 acres · for Google

🕒 May 2025: A Google company bought about 85 acres for $63 million.

Being builtabout 4 miles away

CyrusOne data center on Jug Street Road (New Albany)

New Albany, Licking County

🕒 Sept 2025: CyrusOne held a groundbreaking.

Being builtabout 5 miles away

EdgeConneX data center campus on Innovation Campus Way (New Albany)

New Albany, Licking County

74 acres

🕒 Oct 22, 2026: The Ohio Power Siting Board held a public hearing in New Albany on the third on-site gas…

Built & runningabout 5 miles away

AWS $3.5 billion data center campus (New Albany)

New Albany, Licking County

439 acres · for Amazon Web Services

🕒 Aug 7, 2025: City and AWS said two buildings were finished and the rest were under construction.

Being builtabout 5 miles away

Vantage Data Centers OH1 campus (New Albany)

New Albany, Licking County

70 acres

🕒 Oct 25, 2024: Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.

Reported in the news, not confirmed yet

Stopped or cancelledabout 10 miles away

Amazon (AWS) data center campus in Sunbury Business and Technology Park

Sunbury, Delaware County

for Amazon

🕒 Nov 3, 2026: Sunbury voters approved a charter ban on data centers over 25 megawatts, with about 79% …

🗓️ Public meeting: Jan 5, 2027
Johnstown special election. Anyone can come and speak.
Data center ban charter amendment.
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Johnstown City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Johnstown City. Nothing else.

⚡ Your electric company

Depending on where you live in Johnstown City: Ohio Power Co. (company) or Licking Rural Electric Inc. (co-op (owned by its members)).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.

🙋 Open tasks here

  • Where will the 800 megawatts of power come from, and are new power lines or a gas plant planned?
  • How much water will the campus use?
  • Did the city give a tax break?

How to help →