1 data center project in Johnstown City
Who decides here: the City Council of Johnstown City votes on zoning. The Licking County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Meta data center campus expansion (New Albany, 'Prometheus')
New Albany, Licking County
574 acres · for Meta
🕒 Oct 2026: The Ohio Power Siting Board heard public comments on a proposed fourth gas power plant t…
Proposedabout 4 miles awayKaris Critical 'Smart Farms' data center campus (Beech and Green Chapel roads)
New Albany, Licking County
114 acres
🕒 Jan 2026: Karis asked Ohio EPA for permission to fill wetlands and streams on the site.
Reported in the news, not confirmed yet
Proposedabout 4 miles awayGoogle land on Harrison Road NW (New Albany)
New Albany, Licking County
85 acres · for Google
🕒 May 2025: A Google company bought about 85 acres for $63 million.
Being builtabout 4 miles awayCyrusOne data center on Jug Street Road (New Albany)
New Albany, Licking County
🕒 Sept 2025: CyrusOne held a groundbreaking.
Being builtabout 5 miles awayEdgeConneX data center campus on Innovation Campus Way (New Albany)
New Albany, Licking County
74 acres
🕒 Oct 22, 2026: The Ohio Power Siting Board held a public hearing in New Albany on the third on-site gas…
Built & runningabout 5 miles awayAWS $3.5 billion data center campus (New Albany)
New Albany, Licking County
439 acres · for Amazon Web Services
🕒 Aug 7, 2025: City and AWS said two buildings were finished and the rest were under construction.
Being builtabout 5 miles awayVantage Data Centers OH1 campus (New Albany)
New Albany, Licking County
70 acres
🕒 Oct 25, 2024: Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.
Reported in the news, not confirmed yet
Stopped or cancelledabout 10 miles awayAmazon (AWS) data center campus in Sunbury Business and Technology Park
Sunbury, Delaware County
for Amazon
🕒 Nov 3, 2026: Sunbury voters approved a charter ban on data centers over 25 megawatts, with about 79% …
Johnstown special election. Anyone can come and speak.
What you can do
- Get told first.
We'll email you if anything changes in Johnstown City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Johnstown City: Ohio Power Co. (company) or Licking Rural Electric Inc. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.
🙋 Open tasks here
- Where will the 800 megawatts of power come from, and are new power lines or a gas plant planned?
- How much water will the campus use?
- Did the city give a tax break?