Amazon (AWS) data center campus in Sunbury Business and Technology Park

Amazon planned a $2 billion data center campus in Sunbury's new business park, with the first 450,000-square-foot building to start in 2028. After strong pushback, the city paused all data center work until 2027. Residents want a vote to ban big data centers.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

Where things stand: Stopped or cancelled Paused. Sunbury City Council passed a moratorium on data centers until Jan. 31, 2027. Residents also pushed a ballot measure to ban data centers over 25 megawatts.

  • Nov 3, 2026: Sunbury, Delaware County: referendum decided Source

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Nov 9, 2026.

🕒 Latest update (Nov 3, 2026): Sunbury voters approved a charter ban on data centers over 25 megawatts, with about 79% yes (unofficial results).

What we know

  • 📍 Where11793 Vans Valley Road, in the Sunbury Business and Technology Park between State Route 37 and Vans Valley Road, Sunbury, Delaware County
  • 🏢 CompanyAmazon Web Services
  • 👤 Built forAmazon
  • 🔌 Where the power comes fromAEP Ohio. AWS was negotiating power rates with AEP.
  • 💵 Cost$2 billion
  • 💸 Tax breaks30-year city tax deal (Community Reinvestment Area): 87.5% off property taxes for the first 15 years, then 75% off for 15 more years.
  • 👷 Jobs promised50

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the city's tax deal with Amazon still in force during the moratorium? 🙋 I'll find out ·
  • How much water would the campus use, and from where? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 15, 2026
      Sunbury City Council voted unanimously to pause data centers until Jan. 31, 2027.
    • June 2026
      Residents began collecting signatures for a charter change to ban data centers over 25 megawatts.
    • Nov 3, 2026
      Sunbury voters approved a charter ban on data centers over 25 megawatts, with about 79% yes (unofficial results).

    Local votes and rules

    🗳️ Public vote

    Voters approved a city charter change that bans data centers over 25 megawatts, with about 79% voting yes. Results are unofficial until the county elections board certifies them (expected in late November 2026).

    Nov 3, 2026

    🗳️ Public vote

    Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. Amazon Web Services announced plans for a data center in Sunbury in November 2024.

    Nov 3, 2026

    ⏸️ Pause on new data centers

    City council passed a pause (moratorium) on new data centers. It is set to end in January 2027.

    April 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something