USA β€Ί Ohio β€Ί Delaware County β€Ί Sunbury City
Stopped or cancelled

Amazon (AWS) data center campus in Sunbury Business and Technology Park

Amazon planned a $2 billion data center campus in Sunbury's new business park, with the first 450,000-square-foot building to start in 2028. After strong pushback, the city paused all data center work until 2027. Residents want a vote to ban big data centers.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Paused. Sunbury City Council passed a moratorium on data centers until Jan. 31, 2027. Residents also pushed a ballot measure to ban data centers over 25 megawatts.

πŸ•’ Latest update (June 2026): Residents began collecting signatures for a charter change to ban data centers over 25 megawatts.

What we know

  • πŸ“ Where11793 Vans Valley Road, in the Sunbury Business and Technology Park between State Route 37 and Vans Valley Road, Sunbury, Delaware County
  • 🏒 CompanyAmazon Web Services
  • πŸ‘€ Built forAmazon
  • πŸ”Œ Where the power comes fromAEP Ohio. AWS was negotiating power rates with AEP.
  • πŸ’΅ Cost$2 billion
  • πŸ’Έ Tax breaks30-year city tax deal (Community Reinvestment Area): 87.5% off property taxes for the first 15 years, then 75% off for 15 more years.
  • πŸ‘· Jobs promised50

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 15, 2026
    Sunbury City Council voted unanimously to pause data centers until Jan. 31, 2027.
  • June 2026
    Residents began collecting signatures for a charter change to ban data centers over 25 megawatts.

Local votes and rules

πŸ—³οΈ Public vote

Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. Amazon Web Services announced plans for a data center in Sunbury in November 2024.

Nov 3, 2026

⏸️ Pause on new data centers

City council passed a pause (moratorium) on new data centers. It is set to end in January 2027.

April 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Everything you always wanted to know about Amazon's planned Sunbury development Β· 1808Delaware Β· 2026
  2. Sunbury City Council passes moratorium on data centers Β· WOSU Β· April 16, 2026
  3. Sunbury citizens seek to put data center measure on November ballot Β· NBC4 Β· June 2026

See something wrong? Tell us and we'll fix it.