Karis Critical plans eight data center buildings, about 1.6 million square feet, on 114 acres of farm fields near Johnstown. It asked Ohio EPA to fill about 2 acres of wetlands. Karis builds sites for others and does not run data centers itself.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of New Albany City.
Where things stand: Proposed Land rezoned and annexed in 2025. The company asked Ohio EPA in early 2026 to fill about 2 acres of wetlands.
❓ 2 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (Jan 2026): Karis asked Ohio EPA for permission to fill wetlands and streams on the site.
What we know
- 📍 Where4500 Beech Road NW, New Albany, New Albany, Licking County
- 🏢 CompanyKaris Critical
- 🌳 Size114 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did Ohio EPA approve the wetland permit? 🙋 I'll find out ·
- Who would run the data centers, and how much power and water would they use? 🙋 I'll find out ·
What happened so far
- July 2025The land was approved for rezoning and annexation into New Albany.
- Jan 2026Karis asked Ohio EPA for permission to fill wetlands and streams on the site.
Drag the slider to compare the land before and now.
Where this comes from
- Large data center complex proposed for 114 acres just south of Johnstown · The Reporting Project · Jan 23, 2026
- Karis Critical: New Albany, OH · Baxtel
- Parcel 095-111954-00.000, 4500 Beech Rd NW, owner Karis Critical CMH Smart LLC (113 acres) · Licking County Auditor GIS · Oct 8, 2026
See something wrong? Tell us and we'll fix it.