Being built

Vantage Data Centers OH1 campus (New Albany)

Also called: Vantage OH1

Vantage is building three two-story data centers, 192 megawatts in all, on 70 acres in New Albany. The company says it will invest over $2 billion.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

Where things stand: Broke ground October 2024; first building set to open late 2025, more phases through 2028.

🕒 Latest update (Oct 25, 2024): Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.

What we know

  • 📍 Where3475 Horizon Ct., Silicon Heartland Innovation Park, New Albany, Licking County
  • 🏢 CompanyVantage Data Centers
  • 🌳 Size70 acres
  • ⚡ Power it needs192 megawatts (about as much as 153,600 homes)
  • 💵 Cost$2 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Oct 25, 2024
    Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.
🛰️ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Vantage Data Centers Breaks Ground on 192MW Campus, Enters Growing Ohio Data Center Market · Vantage Data Centers · Oct 25, 2024
  2. OpenStreetMap: Vantage Building 2, 3265 Horizon Court, New Albany · OpenStreetMap contributors · Oct 7, 2026
  3. OpenStreetMap: Vantage Building 1, 3325 Horizon Court · OpenStreetMap contributors · Oct 7, 2026
  4. OpenStreetMap: Vantage Building 3, 3205 Horizon Court · OpenStreetMap contributors · Oct 7, 2026

See something wrong? Tell us and we'll fix it.