Cologix AI data center campus (Johnstown)
Also called: Cologix Johnstown Campus
Cologix is building a $7 billion campus of eight AI data centers on 154 acres in Johnstown, with up to 800 megawatts. The mayor says construction will finish even if voters pass a data center ban in January 2027.
What happens next?
🗓️ Vote: Tuesday, January 5, 2027 (time not announced)
Johnstown special election vote: this project is on the agenda
Data center ban charter amendment.
✔ ConfirmedSourceNot live: please check with the office first.
🗓️ No meeting or deadline known yet.
Where things stand: Being built Under construction inside Johnstown city limits, per the mayor in September 2026. Johnstown voters decide a large data center ban on Jan. 5, 2027.
❓ 3 open questions about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Sept 10, 2026): Johnstown City Council set a Jan. 5, 2027 special election on a charter ban of data centers over 25 megawatts.
What we know
- 📍 Where12017 Duncan Plains Road NW, Johnstown, Johnstown, Licking County
- 🏢 CompanyCologix
- 🌳 Size154 acres
- ⚡ Power it needs800 megawatts (about as much as 640,000 homes)
- 💵 Cost$7 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where will the 800 megawatts of power come from, and are new power lines or a gas plant planned? 🙋 I'll find out ·
- How much water will the campus use? 🙋 I'll find out ·
- Did the city give a tax break? 🙋 I'll find out ·
What happened so far
- Nov 20, 2024Cologix announced it bought 154 acres in Johnstown for an eight-building, 800-megawatt AI data center campus.
- Sept 10, 2026Johnstown City Council set a Jan. 5, 2027 special election on a charter ban of data centers over 25 megawatts.
Drag the slider to compare the land before and now.
Where this comes from
- Cologix Plans $7 Billion, 800-MW Data Center Complex in Ohio · POWER Magazine · Nov 20, 2024
- Data center company Cologix acquires 154 acres in Licking County · WSYX · Nov 21, 2024
- Johnstown City Council approves special election to decide data center ban · The Reporting Project · Sept 10, 2026
- U.S. Census Geocoder result for 12017 Duncan Plains Rd, Johnstown, OH 43031 · U.S. Census Bureau · Oct 7, 2026
- Cologix Johnstown Campus · Data Center Map · 2026
- Cologix expands Central Ohio footprint with land acquisition for new AI-ready 800MW data center campus · Cologix · 2025