2 data center projects in Pataskala City
Who decides here: the City Council of Pataskala City votes on zoning. The Licking County may review big projects too.
In Pataskala City
Microsoft land on Refugee Road (Pataskala)
Pataskala, Licking County
for Microsoft
π Aug 25, 2026: Local reporting described a Microsoft data center as proposed for the Refugee Road site.
Reported in the news, not confirmed yet
Stopped or cancelledAligned Data Centers plan in Pataskala Corporate Park
Pataskala, Licking County
89 acres
π Aug 25, 2026: City council voted 7-0 to reject the site plan, citing missing power details.
Nearby (within 15 miles)
AWS $3.5 billion data center campus (New Albany)
New Albany, Licking County
for Amazon Web Services
π Aug 7, 2025: City and AWS said two buildings were finished and the rest were under construction.
Proposedabout 5 miles awayKaris Critical 'Smart Farms' data center campus (Beech and Green Chapel roads)
New Albany, Licking County
114 acres
π Jan 2026: Karis asked Ohio EPA for permission to fill wetlands and streams on the site.
Reported in the news, not confirmed yet
Being builtabout 5 miles awayEdgeConneX data center campus on Innovation Campus Way (New Albany)
New Albany, Licking County
π April 10, 2026: A case for a third, 430 MW gas plant was opened with the Power Siting Board.
Being builtabout 5 miles awayCyrusOne data center on Jug Street Road (New Albany)
New Albany, Licking County
π Sept 2025: CyrusOne held a groundbreaking.
Being builtabout 6 miles awayVantage Data Centers OH1 campus (New Albany)
New Albany, Licking County
70 acres
π Oct 25, 2024: Vantage broke ground on its $2 billion, 192-megawatt OH1 campus.
Reported in the news, not confirmed yet
Proposedabout 6 miles awayGoogle land on Harrison Road NW (New Albany)
New Albany, Licking County
85 acres Β· for Google
π May 2025: A Google company bought about 85 acres for $63 million.
Local votes and rules
π³οΈ Public vote
Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power. City council had earlier rejected a data center proposal.
What you can do
- Get told first.
We'll email you if anything changes in Pataskala City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Pataskala City: Ohio Power Co. (company) or Licking Rural Electric Inc. (co-op (owned by its members)) or City of Columbus (run by the town).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.
π Open tasks here
- Has Microsoft filed a site plan with Pataskala?
- Would a voter-approved ban apply to this land?
- Will Aligned come back with a new plan?