Microsoft is building a data center on Thornwood Drive in Heath. It had paused the plan in 2025, then restarted it. Residents gathered signatures for a ban on large data centers, but the city would not put it on the November ballot.
Where things stand: Under construction after Microsoft revived plans it paused in April 2025. Heath refused a citizen petition to put a data center ban on the ballot.
๐ Latest update (Sept 2026): Heath officials rejected the petition, saying it lacked valid signatures; petitioners dispute this.
What we know
- ๐ WhereThornwood Drive at Hallie Lane, Heath, Licking County
- ๐ข CompanyMicrosoft
- ๐ค Built forMicrosoft
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts and how much water will the Heath data center use? ๐ I'll find out
- When will it open? ๐ I'll find out
- Will a court or special election decide the Heath ban petition? ๐ I'll find out
What happened so far
- Oct 2024Microsoft announced data centers in New Albany, Hebron and Heath.
- April 2025Microsoft paused its Licking County plans and said the Heath land would be farmed.
- Aug 17, 2026A resident turned in petitions to put a ban on data centers over 25 megawatts on the Heath ballot.
- Sept 2026Heath officials rejected the petition, saying it lacked valid signatures; petitioners dispute this.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Microsoft Hits Pause Button on $1B in Data Centers in Ohio ยท Engineering News-Record ยท April 10, 2025
- Heath rejects petitions to put a data-center ban on the Nov. 3 ballot ยท The Reporting Project ยท Sept 1, 2026
See something wrong? Tell us and we'll fix it.