USA β€Ί Texas β€Ί Williamson County β€Ί Round Rock City

4 data center projects in Round Rock City

Who decides here: the City Council of Round Rock City votes on zoning. The Williamson County may review big projects too.

In Round Rock City

Nearby (within 15 miles)

Built & runningabout 4 miles away

Skybox Austin data center campus (Pflugerville)

Pflugerville, Travis County

πŸ•’ Nov 2023: State filing for Skybox Austin 2 in Pflugerville; construction set for Dec. 2023 to Oct.…

Reported in the news, not confirmed yet

Approved, not built yetabout 6 miles away

Colovore 'Project Raptor' data center (Hutto)

Hutto, Williamson County

πŸ•’ Dec 2024: Hutto City Council granted a site use permit for the data center.

Reported in the news, not confirmed yet

Stopped or cancelledabout 6 miles away

Zydeco 'Project Hutto' data center (Ed Schmidt Blvd, Hutto)

Hutto, Williamson County

πŸ•’ April 2026: Zydeco withdrew its rezoning request; the special Planning and Zoning meeting set for Ap…

Reported in the news, not confirmed yet

Being builtabout 9 miles away

Skybox PowerCampus Austin (Hutto)

Hutto, Williamson County

220 acres

πŸ•’ Nov 2023: State filing for the first Hutto building; construction set for Jan. to Nov. 2024.

Reported in the news, not confirmed yet

Proposedabout 9 miles away

'Project Mustang' data center campus (east of Taylor)

Unincorporated Williamson County, Williamson County

665 acres

πŸ•’ Sept 2026: Developers withdrew their annexation and zoning request with the City of Taylor.

Reported in the news, not confirmed yet

Proposedabout 9 miles away

Iron Mountain 'Taylor Meadows' data center campus (FM 3349, near Hutto and Taylor)

Unincorporated Williamson County, Williamson County

500 acres

πŸ•’ March 2026: Iron Mountain presented the Taylor Meadows project to Hutto City Council with a sewer se…

Reported in the news, not confirmed yet

Local votes and rules

πŸ—ΊοΈ Zoning change

Round Rock City Council unanimously approved a rezoning for a Skybox Datacenters building: about 250,000 square feet and 75 megawatts on 30 acres.

Feb 12, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Round Rock City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Round Rock City. Nothing else.

⚑ Your electric company

Depending on where you live in Round Rock City: Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)) or Bartlett Electric Co-op, Inc. (co-op (owned by its members)) or Oncor Electric Delivery Company LLC (company) or City of Bartlett (not available).

In much of Texas you can pick who sells you power, but this company owns the power lines.

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.

πŸ™‹ Open tasks here

  • Did Round Rock City Council approve the rezoning?
  • How many megawatts will it use?
  • How large will the new buildings be, and how much power will they use?
  • How much water will they use?
  • How much power and water does the campus use in total?
  • Did Round Rock approve the annexation and zoning?
  • Has Amazon filed building plans for the data center?