Sabey Data Centers Austin campus (Round Rock)

Also called: SDC Austin

Sabey Data Centers finished its first Round Rock building in October 2024 and started building a second, three-story building with 54 megawatts, due in 2027. The University of Texas's Texas Advanced Computing Center picked the campus for a new supercomputer.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Round Rock City.

Where things stand: Being built First building finished Oct. 2024; second (54 MW) is being built, due in late 2027.

❓ 1 open question about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (July 2025): Sabey announced its second building, under construction.

What we know

  • 📍 WhereRound Rock, Williamson County
  • 🏢 CompanySabey Data Centers
  • ⚡ Power it needs54 megawatts (about as much as 43,200 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much power and water does the campus use in total? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2024
      Texas Advanced Computing Center chose Sabey's Round Rock campus for a new supercomputer.
    • Oct 2024
      First building completed.
    • July 2025
      Sabey announced its second building, under construction.

    Local votes and rules

    🗺️ Zoning change

    Round Rock City Council unanimously approved a rezoning for a Skybox Datacenters building: about 250,000 square feet and 75 megawatts on 30 acres.

    Feb 12, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Sabey Data Centers to expand campus in Round Rock · Community Impact · Aug 5, 2025
    2. Texas data centers map and list · Cleanview (tracker) · Oct 2026