KDC 'Project Comal' data center campus (Taylor)
Also called: Project Comal
KDC Real Estate plans six data center buildings and two substations on 220 acres at 1051 County Road 401 in Taylor, next to the Samsung chip plant. Reports put it at about 360 megawatts, with power from Oncor. The City Council approved annexing and zoning the land in March 2026.
Where things stand: Taylor City Council approved annexation and zoning unanimously on March 26, 2026.
๐ Latest update (March 26, 2026): Taylor City Council voted unanimously to annex and zone the land for the data center.
What we know
- ๐ Where1051 County Road 401, next to the Samsung plant, Taylor, Williamson County
- ๐ข CompanyKDC Real Estate Development and Investments
- ๐ณ Size220 acres
- โก Power it needs360 megawatts (about as much as 288,000 homes)
- ๐ Where the power comes fromGrid power from Oncor, with two on-site substations
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will it use? ๐ I'll find out
- Did Taylor give a tax break? ๐ I'll find out
- Who is the tenant? ๐ I'll find out
What happened so far
- March 26, 2026Taylor City Council voted unanimously to annex and zone the land for the data center.
Local votes and rules
๐ณ๏ธ Public vote
Residents turned in a petition with more than 1,400 signatures for a citizen ordinance that would pause data centers in Taylor until the city creates a special zoning district for them. City Council did not adopt it or put it on the ballot, saying Texas law does not let cities change zoning by popular vote. Council members said they will handle data centers through the city plan and development code instead.
Drag the slider to compare the land before and now.
Where this comes from
- KDC Wins Approval for 360MW Project Comal Data Center in Taylor, Texas ยท The Job Walk ยท April 6, 2026
See something wrong? Tell us and we'll fix it.