Iron Mountain 'Taylor Meadows' data center campus (FM 3349, near Hutto and Taylor)
Also called: Taylor Meadows
Iron Mountain is planning a campus of up to seven data center buildings and an on-site substation on about 500 acres off FM 3349, south of the Samsung chip plant in Taylor. It asked Hutto for sewer service. The first grid-powered buildings could open around 2030; the company is also looking at on-site natural gas power to open sooner.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Williamson County Commissioners Court (for land outside city and town limits).
Where things stand: Proposed Presented to Hutto City Council in March 2026 as part of a sewer service request.
❓ 3 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (March 2026): Iron Mountain presented the Taylor Meadows project to Hutto City Council with a sewer service request.
What we know
- 📍 WhereOff FM 3349, north of Norman Crossing and south of the Samsung plant, Unincorporated Williamson County, Williamson County
- 🏢 CompanyIron Mountain
- 🌳 Size500 acres
- 🔌 Where the power comes fromGrid power through an on-site substation (around 2030); on-site natural gas also being considered.
- ❄️ CoolingClosed-loop cooling
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the land inside Hutto or Taylor city limits, their ETJ, or the county? 🙋 I'll find out ·
- Will there be an on-site gas power plant? 🙋 I'll find out ·
- How much water will it use? 🙋 I'll find out ·
What happened so far
- March 2026Iron Mountain presented the Taylor Meadows project to Hutto City Council with a sewer service request.
Drag the slider to compare the land before and now.
Where this comes from
- Iron Mountain eyes seven-building data center campus outside Austin, Texas · DatacenterDynamics · March 18, 2026
- Proposed data center seeks wastewater services from Hutto · Community Impact · March 19, 2026