Amazon data center site (County Road 172, Round Rock)
Amazon owns about 149 acres along County Road 172 and McNeil Road, north of State Highway 45. In January 2024, Round Rock City Council annexed and zoned the land, allowing a data center and an electrical substation on the southern half, next to a delivery center. No building plans have been found yet.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Round Rock City.
Where things stand: Approved, not built yet Round Rock City Council approved annexation and zoning on Jan. 11, 2024; no building plans found yet.
❓ 1 open question about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Jan 11, 2024): Round Rock City Council unanimously approved annexation and zoning for the 149-acre site; one part allows a data center and a power substation.
What we know
- 📍 WhereCounty Road 172 and McNeil Road, north of SH 45, Round Rock, Williamson County
- 🏢 CompanyAmazon
- 👤 Built forAmazon Web Services
- 🌳 Size149 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has Amazon filed building plans for the data center? 🙋 I'll find out ·
What happened so far
- Dec 2023Amazon sought a Planning and Zoning recommendation to annex and rezone the land, adding a data center.
- Jan 11, 2024Round Rock City Council unanimously approved annexation and zoning for the 149-acre site; one part allows a data center and a power substation.
Local votes and rules
🗺️ Zoning change
Round Rock City Council unanimously approved a rezoning for a Skybox Datacenters building: about 250,000 square feet and 75 megawatts on 30 acres.
Drag the slider to compare the land before and now.
Where this comes from
- Amazon plans data center in Round Rock, Texas · DatacenterDynamics · Dec 5, 2023
- Round Rock City Council approves zoning for Amazon project · City of Round Rock · Jan 11, 2024
See something wrong? Tell us and we'll fix it.