USA β€Ί Georgia β€Ί Spalding County β€Ί Unincorporated Spalding County

4 data center projects in Unincorporated Spalding County

Who decides here: the Spalding County Board of Commissioners decides on zoning for land outside city and town limits.

In Unincorporated Spalding County

Nearby (within 15 miles)

Local votes and rules

βœ‹ Turned down

Spalding County's planning board unanimously recommended denying the 75 South data center campus: seven two-story buildings totaling 2.24 million square feet plus a power station on about 292 acres along Tomochichi Road. County commissioners were set to take it up May 28, 2026. It would have been the county's fourth data center. A tracker later lists the project as withdrawn.

May 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Unincorporated Spalding County.
  2. Go to county meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Unincorporated Spalding County. Nothing else.

⚑ Your electric company

Depending on where you live in Unincorporated Spalding County: Georgia Power Co. (company) or Central Georgia El Member Corp. (co-op (owned by its members)).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.

πŸ™‹ Open tasks here

  • Will the developer move forward?
  • Who is the end user?
  • Will the developer move forward?
  • How much power will it need?
  • How will the court rule on the lawsuits?
  • The state filing lists 500,000 gallons of water a day; county rules cap closed-loop use near 25,000. Which applies?