4 data center projects in Unincorporated Spalding County
Who decides here: the Spalding County Board of Commissioners decides on zoning for land outside city and town limits.
In Unincorporated Spalding County
Project Spalding data center campus (High Falls Road and Alicia Drive)
Unincorporated Spalding County, Spalding County
132.9 acres
π July 2025: Spalding County commissioners approved the rezoning and special exceptions with conditioβ¦
Approved, not built yetSpalding Investments data center campus (High Falls Road and South McDonough Road)
Unincorporated Spalding County, Spalding County
127.45 acres
π Oct 2025: Spalding County commissioners approved the six-building campus.
Reported in the news, not confirmed yet
Approved, not built yetWallace Jackson data center campus
Unincorporated Spalding County, Spalding County
189.64 acres
π Feb 17, 2026: Nearby residents filed two lawsuits in Spalding County Superior Court to overturn the apβ¦
Stopped or cancelled75 South data center campus (Tomochichi Road)
Unincorporated Spalding County, Spalding County
π Sept 2026: County zoning attorney said the applications were withdrawn.
Nearby (within 15 miles)
Highway 16 Interstate Health Development (data centers plus hospital)
Unincorporated Butts County, Butts County
π Nov 6, 2025: The regional commission issued its finding on the project.
Approved, not built yetabout 10 miles awayHenderson Farms data center campus (Hampton)
Hampton, Henry County
133 acres
π March 24, 2026: A larger Henderson Farms plan with a data center campus and training facility was filed β¦
Being builtabout 10 miles awayEquinix xScale data center campus (Hampton)
Hampton, Henry County
π Aug 2025: Equinix said bulldozers were preparing its Hampton site and it was working with a local β¦
Reported in the news, not confirmed yet
Being builtabout 11 miles awayHampton Technology Park
Hampton, Henry County
603.56 acres
π July 2026: A cemetery group raised concerns that the project is close to the historic O'Neal AME Chβ¦
Proposedabout 13 miles awayAmazon data center land (Lamar County)
Unincorporated Lamar County, Lamar County
for Amazon Web Services
Reported in the news, not confirmed yet
Stopped or cancelledabout 15 miles awayStillwater Technology Park (Lovejoy)
Lovejoy, Clayton County
π Aug 6, 2026: The proposal was formally withdrawn at a special city council meeting.
Local votes and rules
β Turned down
Spalding County's planning board unanimously recommended denying the 75 South data center campus: seven two-story buildings totaling 2.24 million square feet plus a power station on about 292 acres along Tomochichi Road. County commissioners were set to take it up May 28, 2026. It would have been the county's fourth data center. A tracker later lists the project as withdrawn.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Spalding County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Unincorporated Spalding County: Georgia Power Co. (company) or Central Georgia El Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
π Open tasks here
- Will the developer move forward?
- Who is the end user?
- Will the developer move forward?
- How much power will it need?
- How will the court rule on the lawsuits?
- The state filing lists 500,000 gallons of water a day; county rules cap closed-loop use near 25,000. Which applies?