75 South data center campus (Tomochichi Road)
A seven-building, 450-megawatt data center campus was proposed on Tomochichi Road, valued at $6 billion in the state filing. The applications were withdrawn in 2026.
Where things stand: Rezoning and special exception requests withdrawn by Sept. 2026; developers do not plan to return.
🕒 Latest update (Sept 2026): County zoning attorney said the applications were withdrawn.
What we know
- 📍 WhereTomochichi Road, Unincorporated Spalding County, Spalding County
- 🏢 CompanyIndustrial VI Enterprises, LLC (Hillwood / PowerHouse, per tracker)
- ⚡ Power it needs450 megawatts (about as much as 360,000 homes)
- 🔌 Where the power comes fromCentral Georgia EMC (450 MW, per state filing)
- 💵 Cost$6 billion
What happened so far
- Jan 27, 2026Seven-building, 2.24 million square foot campus filed for state regional review (DRI #4607).
- Sept 2026County zoning attorney said the applications were withdrawn.
Local votes and rules
✋ Turned down
Spalding County's planning board unanimously recommended denying the 75 South data center campus: seven two-story buildings totaling 2.24 million square feet plus a power station on about 292 acres along Tomochichi Road. County commissioners were set to take it up May 28, 2026. It would have been the county's fourth data center. A tracker later lists the project as withdrawn.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4607: 75 South Data Center Campus (Development of Regional Impact filing) · Georgia Department of Community Affairs · Jan 27, 2026
- DRI #4607: 75 South Data Center Campus, Additional Information Form · Georgia Department of Community Affairs · Jan 27, 2026
- Are data centers dead in Spalding County? · Griffin Daily News · Sept 3, 2026