Project Spalding data center campus (High Falls Road and Alicia Drive)
Unincorporated Spalding County, Spalding County
132.9 acres
🕒 July 2025: Spalding County commissioners approved the rezoning and special exceptions with conditio…
Approved, not built yetSpalding Investments data center campus (High Falls Road and South McDonough Road)
Unincorporated Spalding County, Spalding County
127.45 acres
🕒 Oct 2025: Spalding County commissioners approved the six-building campus.
Reported in the news, not confirmed yet
Approved, not built yetWallace Jackson data center campus
Unincorporated Spalding County, Spalding County
189.64 acres
🕒 Feb 17, 2026: Nearby residents filed two lawsuits in Spalding County Superior Court to overturn the ap…
Stopped or cancelled75 South data center campus (Tomochichi Road)
Unincorporated Spalding County, Spalding County
🕒 Sept 2026: County zoning attorney said the applications were withdrawn.
Local votes and rules
✋ Turned down · Unincorporated Spalding County
Spalding County's planning board unanimously recommended denying the 75 South data center campus: seven two-story buildings totaling 2.24 million square feet plus a power station on about 292 acres along Tomochichi Road. County commissioners were set to take it up May 28, 2026. It would have been the county's fourth data center. A tracker later lists the project as withdrawn.