Send us a tip
Being built

River Park data center campus (Amazon Web Services)

Also called: River Park

Amazon Web Services is building a 14-building data center campus called River Park in Butts County. In August 2025 the county let parts of two buildings and a substation reach into a stream buffer. Lake residents worry about mud running into the Towaliga River.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Butts County Board of Commissioners (for land outside city and town limits).

Where things stand: Being built Under construction in Aug. 2025, when the county approved fence and stream-buffer variances.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 11, 2025): Butts County commissioners approved an 8-foot fence and let two buildings and a substation reach into the 100-foot stream buffer (3-1 vote).

What we know

  • 📍 WhereOff the new Enterprise Connector, near the Towaliga River and High Falls Lake, Unincorporated Butts County, Butts County
  • 🏢 CompanyRiver Park developer (for Amazon Web Services)
  • 🏛️ Owned byAmazon
  • 👤 Built forAmazon Web Services

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much power and water will the campus use? 🙋 I'll find out ·
  • What tax break did the project get? 🙋 I'll find out ·
  • Is mud from construction reaching High Falls Lake, and who checks? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS aerial imagery of the site (33.267161, -84.084008): large cleared and graded construction area at the pin.

    What happened so far

    • Aug 11, 2025
      Butts County commissioners approved an 8-foot fence and let two buildings and a substation reach into the 100-foot stream buffer (3-1 vote).
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Butts County BOC approves variances for warehouse developments · Jackson Progress-Argus · Aug 16, 2025
    2. OpenStreetMap: Enterprise Connector, River Park E-Commerce Center · OpenStreetMap contributors · Oct 7, 2026
    3. USGS National Map imagery around the existing pin · U.S. Geological Survey · Oct 8, 2026