Being built

Equinix xScale data center campus (Hampton)

Equinix is preparing its first U.S. xScale (very large) data center campus on several hundred acres in Hampton. In August 2025 the company said the land was being graded and power was being arranged. In January 2026 Equinix sold the campus to its xScale joint venture for $459 million.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Hampton City.

Where things stand: Being built Site of several hundred acres was being graded in Aug. 2025.

❓ 2 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Jan 13, 2026): Equinix sold the Hampton data center campus to its xScale joint venture (AMER 3) for $459 million.

What we know

  • 📍 WhereHampton area, about 40 miles from downtown Atlanta, Hampton, Henry County
  • 🏢 CompanyEquinix xScale (joint venture)
  • 🏛️ Owned byEquinix

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Exactly where is the site, and is it the same as Hampton Technology Park? 🙋 I'll find out ·
  • How many megawatts will it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2025
      Equinix said bulldozers were preparing its Hampton site and it was working with a local power company.
    • Jan 13, 2026
      Equinix sold the Hampton data center campus to its xScale joint venture (AMER 3) for $459 million.

    Local votes and rules

    ✅ Approved

    Hampton gave a conditional use permit for a three-building data center on 133 acres north of Georgia 20 at McDonough Street, the first approved in Henry County. Conditions include a 100-foot buffer, screening, a noise study and a $75,000 payment to the city.

    March 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Tuning out the 'bragawatts': Equinix on building a 'generational' DC biz · RCR Wireless News · Aug 13, 2025
    2. Equinix Inc. Form 10-Q (quarter ended June 30, 2026) · U.S. Securities and Exchange Commission · Aug 2026