3 data center projects in Fayetteville City
Who decides here: the City Council of Fayetteville City votes on zoning. The Fayette County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Fayetteville City
QTS Fayetteville data center campus (Project Excalibur)
Fayetteville, Fayette County
615 acres
🕒 June 2026: Flint Riverkeeper and residents announced a Clean Water Act lawsuit over muddy stormwate…
Stopped or cancelledHighway 85 North data center (Crow Holdings)
Fayetteville, Fayette County
37.4 acres
🕒 March 18, 2026: The developer withdrew its appeal, one day before the City Council hearing.
Reported in the news, not confirmed yet
ProposedQTS ATL2 East data center
Fayetteville, Fayette County
313 acres
🕒 April 21, 2026: The regional commission issued its finding on the project.
Nearby (within 15 miles)
Stillwater Technology Park (Lovejoy)
Lovejoy, Clayton County
🕒 Aug 6, 2026: The proposal was formally withdrawn at a special city council meeting.
Approved, not built yetabout 8 miles awayMicrosoft data center (Project Rita, Tyrone)
Tyrone, Fayette County
161 acres · for Microsoft
🕒 Aug 6, 2026: Town staff presented a review of data center rules to the council.
Proposedabout 8 miles awayTA Realty ATL03 / Red Oak data center
Union City, Fulton County
67.8 acres
🕒 Oct 31, 2024: TA Realty filed four data center buildings (about 1 million square feet) for state regio…
Proposedabout 9 miles awayFairburn Technology Center (Bohannon Drive)
Fairburn, Fulton County
59.6 acres
🕒 May 22, 2024: Three data center buildings (1.19 million square feet) filed for state regional review (…
Being builtabout 9 miles awayHampton Technology Park
Hampton, Henry County
603.56 acres
🕒 July 2026: A cemetery group raised concerns that the project is close to the historic O'Neal AME Ch…
Proposedabout 10 miles awayT5 ATL IV data center campus (Gullatt Road, Fairburn)
Fairburn, Fulton County
91 acres
🕒 May 5, 2025: T5 filed T5 ATL IV for state regional review (DRI #4465): up to 2.2 million square feet.
Proposedabout 11 miles awayThe Crossing Business Park data center campus (Union City)
Union City, Fulton County
232.15 acres
🕒 Oct 29, 2026: Union City filed The Crossing Business Park for state regional review (DRI #4825): a dat…
Being builtabout 11 miles awayEquinix xScale data center campus (Hampton)
Hampton, Henry County
🕒 Jan 13, 2026: Equinix sold the Hampton data center campus to its xScale joint venture (AMER 3) for $45…
Local votes and rules
⏸️ Pause on new data centers
After public anger over the approval and growth of the QTS data center campus, Fayetteville's leaders approved a temporary pause on new data center applications in early 2026. Projects already under review were not covered.
✋ Turned down
Fayetteville's planning and zoning commission voted to deny the site plan and building designs for a data center on Highway 85 North, on land already zoned to allow data centers. About 100 residents came to oppose it. The developer, CHI/Acquisitions (Crow Holdings), appealed to the city council but withdrew the appeal before the March 19, 2026 hearing.
What you can do
- Get told first.
We'll email you if anything changes in Fayetteville City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Fayetteville City: Georgia Power Co. (company) or Coweta-fayette El Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Was the Clean Water Act lawsuit filed, and what is its status?
- How much power will the full campus use?
- How many diesel backup generators are planned?
- How much power will it need? The filing said it depends on the customer.