Send us a tip
USA › Georgia › Fayette County › Fayetteville City

3 data center projects in Fayetteville City

Who decides here: the City Council of Fayetteville City votes on zoning. The Fayette County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Fayetteville City

Nearby (within 15 miles)

Stopped or cancelledabout 7 miles away

Stillwater Technology Park (Lovejoy)

Lovejoy, Clayton County

🕒 Aug 6, 2026: The proposal was formally withdrawn at a special city council meeting.

Approved, not built yetabout 8 miles away

Microsoft data center (Project Rita, Tyrone)

Tyrone, Fayette County

161 acres · for Microsoft

🕒 Aug 6, 2026: Town staff presented a review of data center rules to the council.

Proposedabout 8 miles away

TA Realty ATL03 / Red Oak data center

Union City, Fulton County

67.8 acres

🕒 Oct 31, 2024: TA Realty filed four data center buildings (about 1 million square feet) for state regio…

Proposedabout 9 miles away

Fairburn Technology Center (Bohannon Drive)

Fairburn, Fulton County

59.6 acres

🕒 May 22, 2024: Three data center buildings (1.19 million square feet) filed for state regional review (…

Being builtabout 9 miles away

Hampton Technology Park

Hampton, Henry County

603.56 acres

🕒 July 2026: A cemetery group raised concerns that the project is close to the historic O'Neal AME Ch…

Proposedabout 10 miles away

T5 ATL IV data center campus (Gullatt Road, Fairburn)

Fairburn, Fulton County

91 acres

🕒 May 5, 2025: T5 filed T5 ATL IV for state regional review (DRI #4465): up to 2.2 million square feet.

Proposedabout 11 miles away

The Crossing Business Park data center campus (Union City)

Union City, Fulton County

232.15 acres

🕒 Oct 29, 2026: Union City filed The Crossing Business Park for state regional review (DRI #4825): a dat…

Being builtabout 11 miles away

Equinix xScale data center campus (Hampton)

Hampton, Henry County

🕒 Jan 13, 2026: Equinix sold the Hampton data center campus to its xScale joint venture (AMER 3) for $45…

Local votes and rules

⏸️ Pause on new data centers

After public anger over the approval and growth of the QTS data center campus, Fayetteville's leaders approved a temporary pause on new data center applications in early 2026. Projects already under review were not covered.

Feb 2026Source

✋ Turned down

Fayetteville's planning and zoning commission voted to deny the site plan and building designs for a data center on Highway 85 North, on land already zoned to allow data centers. About 100 residents came to oppose it. The developer, CHI/Acquisitions (Crow Holdings), appealed to the city council but withdrew the appeal before the March 19, 2026 hearing.

Jan 27, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Fayetteville City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Fayetteville City. Nothing else.

⚡ Your electric company

Depending on where you live in Fayetteville City: Georgia Power Co. (company) or Coweta-fayette El Member Corp. (co-op (owned by its members)).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.

🙋 Open tasks here

  • Was the Clean Water Act lawsuit filed, and what is its status?
  • How much power will the full campus use?
  • How many diesel backup generators are planned?
  • How much power will it need? The filing said it depends on the customer.
  • Does it need any new city vote?

How to help →