QTS Fayetteville data center campus (Project Excalibur)
Also called: Project Excalibur, QTS Atlanta-Fayetteville
QTS is building a huge data center campus on about 615 acres in Fayetteville. The state filing describes 16 buildings and $6.5 billion. Neighbors and Flint Riverkeeper say muddy runoff from construction has polluted their land and a creek.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Fayetteville City.
Where things stand: Being built Under construction since 2023. Flint Riverkeeper and neighbors sent a 60-day notice to sue over muddy runoff in summer 2026, and QTS reached out to talk. We found no filed lawsuit as of Nov. 2026.
❓ 3 open questions about it: see below.
Last checked Nov 9, 2026.
🕒 Latest update (June 2026): Flint Riverkeeper and residents announced a Clean Water Act lawsuit over muddy stormwater flowing onto homes and a creek.
What we know
- 📍 WhereNorthwest corner of Ga. Highway 54 and Veterans Parkway, Fayetteville, Fayette County
- 🏢 CompanyQTS Data Centers (filed by National Acquisition Company, LLC)
- 🏛️ Owned byBlackstone
- 🌳 Size615 acres
- ⚡ Power it needs250 megawatts (about as much as 200,000 homes)
- 💧 WaterFayette County Water System · 570,000 gallons a day
- 💵 Cost$6.5 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Was the Clean Water Act lawsuit filed, and what is its status? 🙋 I'll find out ·
- How much power will the full campus use? 🙋 I'll find out ·
- How many diesel backup generators are planned? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked USGS aerial imagery of the site (33.446781, -84.5222): the imagery predates the 2023 start of construction and still shows woods and fields; the state filing's GPS point confirms the site.
- Nov 9, 2026: We checked the news for a filed Clean Water Act lawsuit against QTS in Fayetteville and found none. An August 2026 report said QTS had reached out to discuss a resolution.
What happened so far
- Sept 12, 2022Project Excalibur filed for state review (DRI #3813): 16 buildings, 7 million square feet.
- 2023Construction began.
- June 2026Flint Riverkeeper and residents announced a Clean Water Act lawsuit over muddy stormwater flowing onto homes and a creek.
Local votes and rules
⏸️ Pause on new data centers
After public anger over the approval and growth of the QTS data center campus, Fayetteville's leaders approved a temporary pause on new data center applications in early 2026. Projects already under review were not covered.
✋ Turned down
Fayetteville's planning and zoning commission voted to deny the site plan and building designs for a data center on Highway 85 North, on land already zoned to allow data centers. About 100 residents came to oppose it. The developer, CHI/Acquisitions (Crow Holdings), appealed to the city council but withdrew the appeal before the March 19, 2026 hearing.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #3813: Project Excalibur (Development of Regional Impact filing) · Georgia Department of Community Affairs · Sept 12, 2022
- QTS Plans World's Largest Data Center Campus in Fayetteville · Atlanta Small Business Network · Aug 24, 2022
- Flint Riverkeeper and Fayetteville residents plan to file lawsuit against data center developers · The Newnan Times-Herald · June 15, 2026
- DRI #3813 Initial Information Form: Project Excalibur (GPS 33.446781, -84.5222) · Georgia Department of Community Affairs · Oct 8, 2026
- Watchdog group threatens to sue data center over Georgia water pollution · Atlanta News First · Aug 13, 2026
See something wrong? Tell us and we'll fix it.