QTS plans another 2 million-square-foot data center on about 313 acres in Fayetteville, next to its big campus. The filing says $3 billion, about 200,000 gallons of water a day, and a new on-site substation and power lines.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Fayetteville City.

Where things stand: Proposed Filed for state review in Jan. 2026; regional finding issued April 2026.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (April 21, 2026): The regional commission issued its finding on the project.

What we know

  • 📍 WhereAbout 313 acres west of Veterans Parkway, Fayetteville, Fayette County
  • 🏢 CompanyQTS Eastwood, LLC
  • 🏛️ Owned byQTS Data Centers (Blackstone)
  • 🌳 Size313 acres
  • 🔌 Where the power comes fromGeorgia Power. A new substation and new power lines would be built on the site.
  • 🗼 New power linesYes
  • 💧 WaterFayette County Water System · 200,000 gallons a day
  • 💵 Cost$3 billion
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much power will it need? The filing said it depends on the customer. 🙋 I'll find out ·
  • Does it need any new city vote? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 13, 2026
      QTS filed a 2 million square foot data center for state regional review (DRI #4603).
    • April 21, 2026
      The regional commission issued its finding on the project.

    Local votes and rules

    ⏸️ Pause on new data centers

    After public anger over the approval and growth of the QTS data center campus, Fayetteville's leaders approved a temporary pause on new data center applications in early 2026. Projects already under review were not covered.

    Feb 2026

    ✋ Turned down

    Fayetteville's planning and zoning commission voted to deny the site plan and building designs for a data center on Highway 85 North, on land already zoned to allow data centers. About 100 residents came to oppose it. The developer, CHI/Acquisitions (Crow Holdings), appealed to the city council but withdrew the appeal before the March 19, 2026 hearing.

    Jan 27, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4603: ATL2 East (Development of Regional Impact filing) · Georgia Department of Community Affairs · Jan 13, 2026
    2. DRI #4603: ATL2 East, Additional Information Form · Georgia Department of Community Affairs · Jan 13, 2026

    See something wrong? Tell us and we'll fix it.