Highway 85 North data center (Crow Holdings)
Crow Holdings planned one two-story data center (300,000 square feet) and a substation on Highway 85 North. Fayetteville's planning and zoning commission rejected the site plan, and the developer withdrew its appeal to the city council.
Where things stand: Planning commission rejected the site plan; the developer then withdrew its appeal.
What we know
- π Where37.4 acres on Highway 85 North, north of Fayette Pavilion, Fayetteville, Fayette County
- π’ CompanyCrow Holdings Development and CHI/Acquisitions, LP
- π³ Size37.4 acres
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- When exactly was the appeal withdrawn? π I'll find out
Local votes and rules
βΈοΈ Pause on new data centers
After public anger over the approval and growth of the QTS data center campus, Fayetteville's leaders approved a temporary pause on new data center applications in early 2026. Projects already under review were not covered.
β Turned down
Fayetteville's planning and zoning commission voted to deny the site plan and building designs for a data center on Highway 85 North, on land already zoned to allow data centers. About 100 residents came to oppose it. The developer, CHI/Acquisitions (Crow Holdings), appealed to the city council but withdrew the appeal before the March 19, 2026 hearing.
Drag the slider to compare the land before and now.
Where this comes from
- Developer effectively withdraws application for data center in Fayetteville, Georgia Β· Data Center Dynamics
See something wrong? Tell us and we'll fix it.